Assessment Year | 2011 |
---|---|
Principal Product | Sheet Metal Ducts |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 61 |
Plant Area |
92,700
ft2
|
Annual Production | 5,842,482
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,338 | 777,136 |
kWh
|
$0.062 |
Electricity Demand | $14,396 | 2,198 |
kW-mo/yr
|
$6.55 |
Natural Gas | $22,873 | 2,554 |
MMBtu
|
$8.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,882 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,819 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $1,244 | $500 |
$1,244
20,000
kWh
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $534 | - |
$327
5,265
kWh
|
$207
-
kW-mo/yr
|
- | |
03 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $4,285 | $4,000 |
$2,626
42,226
kWh
|
$1,659
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $286 | $1,500 |
$175
2,821
kWh
|
$111
-
kW-mo/yr
|
- | |
05 | 2.7423: Reduce heat gain by window tinting | $533 | - | - | - |
$533
-
MMBtu
|
|
TOTAL RECOMMENDED | $6,882 | $6,000 |
$4,372
70,312
kWh
|
$1,977
-
kW-mo/yr
|
$533
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,819 | $4,000 |
$2,953
47,491
kWh
|
$1,866
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs