ITAC Assessment: UD0844
ITAC logo
ITAC Assessment: UD0844
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Hydraulic hose, fittings,couplings
NAICS 326122: Plastics Pipe and Pipe Fitting Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 493,000
ft2
Annual Production 5,799
ton
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $906,293 24,696,850
kWh
Electricity Demand $676,915 43,584
kW-mo/yr
Natural Gas $554,732 100,050
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $385,454 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,709

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Water Consumption Savings
01 3.4111: Use closed cycle process to minimize waste water production $170,257 $280,000 $(-1,212.0)
(-31,223)
kWh
$(-2,346.0)
-
kW-mo/yr
- - $128,623
-
Tgal
- $45,192
-
Tgal
02 3.1221: Use reactive rinsing $70,989 $30,000 - - - - $52,532
-
Tgal
- $18,457
-
Tgal
03 2.3212: Optimize plant power factor $11,543 $16,000 - - $11,543 - - - -
04 2.6218: Turn off equipment when not in use $33,247 $2,000 $33,247
870,333
kWh
- - - - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,557 - $1,441
37,129
kWh
$1,116
-
kW-mo/yr
- - - - -
06 2.4224: Upgrade controls on compressors $20,051 $18,555 $12,751
326,943
kWh
$7,300
-
kW-mo/yr
- - - - -
07 2.4239: Eliminate or reduce compressed air usage $7,542 - $4,796
122,982
kWh
$2,746
-
kW-mo/yr
- - - - -
08 2.4221: Install compressor air intakes in coolest locations $3,988 $5,000 $2,532
65,226
kWh
$1,456
-
kW-mo/yr
- - - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,616 $500 $1,216
31,332
kWh
$700
-
kW-mo/yr
- - - $(-300.0) -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $267 - $148
3,814
kWh
$119
-
kW-mo/yr
- - - - -
11 2.1233: Analyze flue gas for proper air/fuel ratio $13,123 $1,000 - - - $13,123
-
MMBtu
- - -
12 2.2414: Use waste heat from hot flue gases to preheat $10,508 $16,000 - - - $10,508
-
MMBtu
- - -
13 2.2211: Use optimum temperature $3,225 - - - - $3,225
-
MMBtu
- - -
14 2.7221: Lower temperature during the winter season and vice-versa $18,762 - - - - $18,762
-
MMBtu
- - -
15 2.7314: Reduce ventilation air $17,779 - $1,251
32,227
kWh
- - $16,528
-
MMBtu
- - -
TOTAL RECOMMENDED $385,454 $369,055 $56,170
1,458,763
kWh
$11,091
-
kW-mo/yr
$11,543 $62,146
-
MMBtu
$181,155
-
Tgal
$(-300.0) $63,649
-
Tgal
TOTAL IMPLEMENTED $34,709 $1,000 $1,589
40,943
kWh
$1,235
-
kW-mo/yr
- $31,885
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs