Assessment Year | 2010 |
---|---|
Principal Product | Gas Burners and Heat Exchangers |
NAICS | 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing |
SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
120,000
ft2
|
Annual Production | 71,600,000
pieces
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $315,846 | 3,489,014 |
kWh
|
$0.091 |
Natural Gas | $36,120 | 2,794 |
MMBtu
|
$12.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $315,732 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,483 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $609 | $609 | - |
$609
-
kW-mo/yr
|
- | - | - | |
02 | 2.9121: Install wind powered electric generator | $244,092 | $1,216,000 |
$50,209
788,217
kWh
|
- | $193,883 | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,399 | $8,760 |
$11,227
171,925
kWh
|
$961
-
kW-mo/yr
|
- | - | $211 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $31,724 | $24,375 |
$29,387
450,036
kWh
|
$3,213
-
kW-mo/yr
|
- | - | $(-876.0) | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $677 | $125 |
$597
9,375
kWh
|
$80
-
kW-mo/yr
|
- | - | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $2,400 | $2,000 |
$2,400
37,500
kWh
|
- | - | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $2,219 | $5,273 |
$2,219
24,650
kWh
|
- | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,449 | $500 |
$2,930
46,000
kWh
|
$394
-
kW-mo/yr
|
- | - | $(-1,875.0) | |
09 | 2.4322: Use or replace with energy efficient substitutes | $13,033 | $39,100 | - | - | - |
$13,033
-
MMBtu
|
- | |
10 | 2.7224: Reduce space conditioning during non-working hours | $3,483 | $63 |
$768
11,763
kWh
|
- | - |
$2,715
-
MMBtu
|
- | |
11 | 2.7224: Reduce space conditioning during non-working hours | $2,147 | $2,100 | - | - | - |
$2,147
-
MMBtu
|
- | |
12 | 2.7235: Install fossil fuel make-up air unit | $1,500 | $14,900 | - | - | - |
$1,500
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $315,732 | $1,313,805 |
$99,737
1,539,466
kWh
|
$5,257
-
kW-mo/yr
|
$193,883 |
$19,395
-
MMBtu
|
$(-2,540.0) | ||
TOTAL IMPLEMENTED | $3,483 | $63 |
$768
11,763
kWh
|
- | - |
$2,715
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs