ITAC Assessment: UD0814
ITAC logo
ITAC Assessment: UD0814
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Custom Molding of Plastic Tanks
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 208,600
ft2
Annual Production 401,170
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $252,053 3,717,120
kWh
Electricity Demand $63,013 740
kW-mo/yr
Natural Gas $458,909 53,836
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $93,056 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $60,707

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $36,324 $60,476 $30,598
419,724
kWh
$6,371
-
kW-mo/yr
- $(-645.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,387 $28,012 $3,631
49,804
kWh
$756
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,684 $21,115 $10,498
144,000
kWh
$2,186
-
kW-mo/yr
- -
04 2.4151: Develop a repair/replace policy $899 $1,724 $744
10,200
kWh
$155
-
kW-mo/yr
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $386 - $238
3,260
kWh
$148
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,642 $1,000 $2,187
30,000
kWh
$455
-
kW-mo/yr
- -
07 2.4322: Use or replace with energy efficient substitutes $137 $540 $114
1,562
kWh
$23
-
kW-mo/yr
- -
08 2.2511: Insulate bare equipment $18,417 $9,030 - - $18,417
-
MMBtu
-
09 2.2532: Use only amount of air necessary to prevent explosion hazard $8,568 $3,000 - - $8,568
-
MMBtu
-
10 2.2414: Use waste heat from hot flue gases to preheat $4,017 $400 - - $4,017
-
MMBtu
-
11 2.2511: Insulate bare equipment $1,111 $807 $920
12,600
kWh
$191
-
kW-mo/yr
- -
12 2.7311: Ventilation system to shut off when room is not in use $3,484 - - - $3,484
-
MMBtu
-
TOTAL RECOMMENDED $93,056 $126,104 $48,930
671,150
kWh
$10,285
-
kW-mo/yr
$34,486
-
MMBtu
$(-645.0)
TOTAL IMPLEMENTED $60,707 $94,612 $37,398
512,988
kWh
$7,885
-
kW-mo/yr
$16,069
-
MMBtu
$(-645.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs