ITAC Assessment: UD0811
ITAC logo
ITAC Assessment: UD0811
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Aluminum, stainless and carbon slit coils and sheets
NAICS 331221: Rolled Steel Shape Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $50
M
to 100
M
# of Employees 50
Plant Area 180,000
ft2
Annual Production 70,000
ton
Production Hrs. Annual 3,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,194 1,358,776
kWh
Electricity Demand $89,961 491
kW-mo/yr
Natural Gas $44,936 3,856
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,361 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.8114: Change rate schedules or other changes in utility service $27,175 - - - $27,175 -
02 2.7444: Close holes and openings in building such as broken windows $7,064 $13,132 - - - $7,064
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $897 $1,000 $640
10,666
kWh
$257
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $646 - $461
7,684
kWh
$185
-
kW-mo/yr
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,579 $50,000 $4,680
78,000
kWh
$7,899
-
kW-mo/yr
- -
TOTAL RECOMMENDED $48,361 $64,132 $5,781
96,350
kWh
$8,341
-
kW-mo/yr
$27,175 $7,064
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs