ITAC Assessment: UD0809
ITAC logo
ITAC Assessment: UD0809
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Custom profile extrustions for decking and railing
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 120,000
ft2
Annual Production 27,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $308,947 8,742,150
kWh
Electricity Demand $211,385 1,411
kW-mo/yr
Natural Gas $31,526 3,046
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,229 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $60,126

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.7313: Recycle air for heating, ventilation and air conditioning $22,565 $5,640 $9,923
283,500
kWh
$3,681
-
kW-mo/yr
- $8,961
-
MMBtu
- -
02 2.4133: Use most efficient type of electric motors $20,495 $120,000 $9,114
260,400
kWh
$3,381
-
kW-mo/yr
- - - $8,000
03 2.3212: Optimize plant power factor $15,628 $20,000 - - $15,628 - - -
04 2.6218: Turn off equipment when not in use $8,423 - $8,423
240,660
kWh
- - - - -
05 2.4239: Eliminate or reduce compressed air usage $6,288 $324 $4,586
131,040
kWh
$1,702
-
kW-mo/yr
- - - -
06 2.4239: Eliminate or reduce compressed air usage $5,845 $1,000 $4,263
121,800
kWh
$1,582
-
kW-mo/yr
- - - -
07 2.6218: Turn off equipment when not in use $4,812 - $1,302
100,296
kWh
$3,510
-
kW-mo/yr
- - - -
08 2.6231: Utilize controls to operate equipment only when needed $4,116 $23,400 $4,116
117,600
kWh
- - - - -
09 2.2511: Insulate bare equipment $2,822 $1,440 $2,058
58,800
kWh
$764
-
kW-mo/yr
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,765 $1,048 $2,018
57,666
kWh
$749
-
kW-mo/yr
- - - $(-2.0)
11 3.4154: Eliminate leaks in water lines and valves $1,858 $480 - - - - $1,858
-
Tgal
-
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,411 $8,270 $382
29,400
kWh
$1,029
-
kW-mo/yr
- - - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $1,348 $1,703 $730
21,470
kWh
$279
-
kW-mo/yr
- - - $339
14 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,678 $5,467 $2,678
25,884
kWh
- - - - -
15 2.4231: Reduce the pressure of compressed air to the minimum required $685 - $500
14,280
kWh
$185
-
kW-mo/yr
- - - -
16 2.7122: Disconnect ballasts $532 - $388
11,088
kWh
$144
-
kW-mo/yr
- - - -
17 2.6218: Turn off equipment when not in use $414 - $414
11,827
kWh
- - - - -
18 2.2625: Chill water to the highest temperature possible $363 - $265
7,560
kWh
$98
-
kW-mo/yr
- - - -
19 2.2414: Use waste heat from hot flue gases to preheat $181 $500 - - - $181
-
MMBtu
- -
TOTAL RECOMMENDED $103,229 $189,272 $51,160
1,493,271
kWh
$17,104
-
kW-mo/yr
$15,628 $9,142
-
MMBtu
$1,858
-
Tgal
$8,337
TOTAL IMPLEMENTED $60,126 $151,791 $34,738
993,123
kWh
$8,090
-
kW-mo/yr
- $8,961
-
MMBtu
- $8,337
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs