Assessment Year | 2009 |
---|---|
Principal Product | Carbonated Soft Drinks |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
233,000
ft2
|
Annual Production | 22,000,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $439,086 | 5,280,600 |
kWh
|
$0.083 |
Natural Gas | $341,952 | 34,389 |
MMBtu
|
$9.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $155,274 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,732 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $39,022 | $12,000 |
$17,444
513,046
kWh
|
$21,578
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $21,769 | $25,000 | - | - | $21,769 | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,619 | $17,147 |
$9,997
294,018
kWh
|
$6,024
-
kW-mo/yr
|
- | - | - | $598 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,872 | $25,117 |
$5,936
174,593
kWh
|
$4,533
-
kW-mo/yr
|
- | - | - | $1,403 | |
05 | 2.2437: Recover waste heat from equipment | $10,974 | $2,000 | - | - | - |
$10,974
-
MMBtu
|
- | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $10,710 | $16,000 | - | - | - |
$10,710
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,327 | $8,043 |
$4,722
138,868
kWh
|
$3,605
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,938 | $6,703 |
$3,935
115,723
kWh
|
$3,003
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.1241: Reduce excessive boiler blowdown | $5,312 | $5,000 | - | - | - |
$5,312
-
MMBtu
|
- | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $4,119 | - |
$2,247
66,100
kWh
|
$1,872
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.2511: Insulate bare equipment | $3,797 | $4,283 | - | - | - |
$3,797
-
MMBtu
|
- | - | |
12 | 2.8118: Check for accuracy of utility / power meters | $3,741 | - | - | - | $3,741 | - | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,689 | - |
$1,603
47,156
kWh
|
$1,224
-
kW-mo/yr
|
- | - | - | $862 | |
14 | 2.4226: Use / purchase optimum sized compressor | $2,965 | - |
$2,965
87,194
kWh
|
- | - | - | - | - | |
15 | 2.3212: Optimize plant power factor | $1,903 | $5,000 | - | - | $1,903 | - | - | - | |
16 | 2.4221: Install compressor air intakes in coolest locations | $1,428 | $1,000 |
$709
20,862
kWh
|
$719
-
kW-mo/yr
|
- | - | - | - | |
17 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,423 | - | - | - | - | - |
$1,423
-
Tgal
|
- | |
18 | 2.2522: Isolate hot or cold equipment | $666 | - | - | - | - |
$666
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $155,274 | $127,293 |
$49,558
1,457,560
kWh
|
$42,558
-
kW-mo/yr
|
$27,413 |
$31,459
-
MMBtu
|
$1,423
-
Tgal
|
$2,863 | ||
TOTAL IMPLEMENTED | $65,732 | $67,293 |
$32,114
944,514
kWh
|
$20,980
-
kW-mo/yr
|
- |
$9,775
-
MMBtu
|
- | $2,863 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs