ITAC Assessment: UD0791
ITAC logo
ITAC Assessment: UD0791
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Rubber Flooring
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 105,000
ft2
Annual Production 8,500,000
lb
Production Hrs. Annual 2,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $455,652 4,034,918
kWh
Natural Gas $666,469 65,146
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $372,794 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $289,559

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.1231: Establish burner maintenance schedule for boilers $180,324 $20,000 - - $180,324
-
MMBtu
- -
02 2.2114: Shut off steam traps on super heated steam lines when not in use $66,274 - - - $69,274
-
MMBtu
$(-3,000.0) -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $43,743 $28,000 $33,462
298,771
kWh
- $10,281
-
MMBtu
- -
04 2.4226: Use / purchase optimum sized compressor $12,848 - $12,848
458,858
kWh
- - - -
05 4.821: Pay bills on time to avoid late fees $11,737 - - $11,737 - - -
06 2.2136: Install / repair insulation on steam lines $11,734 $2,358 - - $11,734
-
MMBtu
- -
07 2.1243: Use heat from boiler blowdown to preheat boiler feed water $11,202 $336 - - $11,202
-
MMBtu
- -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,772 $15,000 $9,772
87,250
kWh
- - - -
09 2.4224: Upgrade controls on compressors $7,364 $15,000 $7,364
65,750
kWh
- - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,648 $2,164 $4,648
41,500
kWh
- - - -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,940 $8,000 $2,940
26,250
kWh
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $2,512 $12,625 $2,380
21,250
kWh
- - - $132
13 2.7142: Utilize higher efficiency lamps and/or ballasts $2,250 $7,735 $2,294
20,480
kWh
- - - $(-44.0)
14 2.7142: Utilize higher efficiency lamps and/or ballasts $1,996 $6,668 $1,762
45,733
kWh
- - - $234
15 2.2153: Close off unneeded steam lines $1,974 $1,100 - - $1,974
-
MMBtu
- -
16 2.4231: Reduce the pressure of compressed air to the minimum required $924 - $924
8,250
kWh
- - - -
17 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $552 $1,000 $1,568
14,000
kWh
- - $(-816.0) $(-200.0)
TOTAL RECOMMENDED $372,794 $119,986 $79,962
1,088,092
kWh
$11,737 $284,789
-
MMBtu
$(-3,816.0) $122
TOTAL IMPLEMENTED $289,559 $24,600 $19,064
514,358
kWh
$11,737 $262,774
-
MMBtu
$(-3,816.0) $(-200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs