ITAC Assessment: UD0769
ITAC logo
ITAC Assessment: UD0769
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Power Transmission Components
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 652
Plant Area 432,573
ft2
Annual Production 290,000
units
Production Hrs. Annual 7,200
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,162,065 23,236,252
kWh
Natural Gas $507,129 40,996
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $559,161 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $518,058

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.6218: Turn off equipment when not in use $126,798 - $126,798
3,345,602
kWh
- - - -
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $119,000 - - - $119,000
-
MMBtu
- -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $63,509 $110,000 $44,783
1,181,613
kWh
$13,062
-
kW-mo/yr
- - $5,664
04 2.7142: Utilize higher efficiency lamps and/or ballasts $61,170 $110,000 $42,569
1,123,200
kWh
$14,452
-
kW-mo/yr
- - $4,149
05 2.7231: Use radiant heater for spot heating $44,667 $28,125 - - $44,667
-
MMBtu
- -
06 2.2414: Use waste heat from hot flue gases to preheat $39,200 $130,000 - - $39,200
-
MMBtu
- -
07 2.6218: Turn off equipment when not in use $25,268 - $12,720
334,731
kWh
- $12,548
-
MMBtu
- -
08 2.1113: Reduce combustion air flow to optimum $23,200 $400 - - $23,200
-
MMBtu
- -
09 2.1113: Reduce combustion air flow to optimum $13,400 $600 - - $13,400
-
MMBtu
- -
10 2.2424: Use heat in flue gases to preheat products or materials $10,000 $25,000 - - $10,000
-
MMBtu
- -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,569 $3,275 $3,411
90,000
kWh
$1,158
-
kW-mo/yr
- - -
12 2.7314: Reduce ventilation air $17,703 $26,910 - - $17,703
-
MMBtu
- -
13 2.4224: Upgrade controls on compressors $3,980 - $3,980
105,000
kWh
- - - -
14 2.7314: Reduce ventilation air $2,208 $590 $2,208
58,254
kWh
- - - -
15 3.4116: Meter recycled water (to reduce sewer charges) $1,800 $500 - - - $1,800
-
Tgal
-
16 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,447 $520 $1,080
28,512
kWh
$367
-
kW-mo/yr
- - -
17 2.6218: Turn off equipment when not in use $1,242 - $921
24,300
kWh
$321
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $559,161 $435,920 $238,470
6,291,212
kWh
$29,360
-
kW-mo/yr
$279,718
-
MMBtu
$1,800
-
Tgal
$9,813
TOTAL IMPLEMENTED $518,058 $383,410 $238,470
6,291,212
kWh
$29,360
-
kW-mo/yr
$238,615
-
MMBtu
$1,800
-
Tgal
$9,813
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs