Assessment Year | 2007 |
---|---|
Principal Product | Resin and Latex |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
112,000
ft2
|
Annual Production | 22,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $368,548 | 6,997,734 |
kWh
|
$0.053 |
Other Energy | $653,420 | 82,042 |
MMBtu
|
$7.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $321,859 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $173,048 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2223: Enhance sensitivity of temperature control and cutoff | $73,500 | $147,000 | - | - | - |
$73,500
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $57,728 | $10,396 |
$36,288
362,880
kWh
|
- | - | - | $21,440 | |
03 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $49,140 | $253,091 |
$109,200
1,902,000
kWh
|
- |
$(-141,456.0)
-
MMBtu
|
$97,776
-
MMBtu
|
$(-16,380.0) | |
04 | 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat | $46,585 | $42,000 |
$46,585
465,847
kWh
|
- | - | - | - | |
05 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $33,617 | $337,437 |
$109,200
1,902,000
kWh
|
- |
$(-141,456.0)
-
MMBtu
|
$82,253
-
MMBtu
|
$(-16,380.0) | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,952 | $19,500 |
$14,553
145,530
kWh
|
- | - | - | $399 | |
07 | 2.4224: Upgrade controls on compressors | $12,600 | $15,000 |
$12,600
126,000
kWh
|
- | - | - | - | |
08 | 2.3137: Use power during off-peak periods | $12,404 | - | - |
$12,404
-
kW-mo/yr
|
- | - | - | |
09 | 2.2437: Recover waste heat from equipment | $11,340 | $2,000 | - | - | - |
$11,340
-
MMBtu
|
- | |
10 | 2.2515: Use optimum thickness insulation | $4,545 | $16,005 | - | - | - |
$4,545
-
MMBtu
|
- | |
11 | 2.4224: Upgrade controls on compressors | $2,520 | - |
$2,520
25,200
kWh
|
- | - | - | - | |
12 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,928 | $42,500 | - | - | - |
$2,928
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $321,859 | $884,929 |
$330,946
4,929,457
kWh
|
$12,404
-
kW-mo/yr
|
$(-282,912.0)
-
MMBtu
|
$272,342
-
MMBtu
|
$(-10,921.0) | ||
TOTAL IMPLEMENTED | $173,048 | $236,396 |
$63,441
634,410
kWh
|
- | - |
$87,768
-
MMBtu
|
$21,839 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs