Assessment Year | 2007 |
---|---|
Principal Product | Bi-Metallic Bushings and Thrust Washers |
NAICS | 336991: Motorcycle, Bicycle, and Parts Manufacturing |
SIC | 3940: |
Sales Range | $50 M to 100M |
# of Employees | 295 |
Plant Area |
223,740
ft2
|
Annual Production | 342,386,767
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $960,916 | 20,010,558 |
kWh
|
$0.048 |
Natural Gas | $970,112 | 72,998 |
MMBtu
|
$13.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $343,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $227,960 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $135,639 | $80,000 | - |
$135,639
-
MMBtu
|
- | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $78,829 | - | - | - | - | - | $78,829 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $74,891 | $305,325 |
$69,300
1,380,000
kWh
|
- | - | $5,591 | - | |
04 | 3.4151: Minimize water usage | $17,430 | $700 | - |
$10,300
-
MMBtu
|
$7,130
-
Tgal
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $15,400 | - |
$15,400
308,000
kWh
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $15,104 | $5,930 |
$14,360
287,100
kWh
|
$744
-
MMBtu
|
- | - | - | |
07 | 2.2424: Use heat in flue gases to preheat products or materials | $2,977 | $11,246 | - |
$2,977
-
MMBtu
|
- | - | - | |
08 | 2.2514: Cover open tanks | $2,295 | $355 | - |
$2,150
-
MMBtu
|
$145
-
Tgal
|
- | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $825 | $64 |
$825
16,500
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $343,390 | $403,620 |
$99,885
1,991,600
kWh
|
$151,810
-
MMBtu
|
$7,275
-
Tgal
|
$5,591 | $78,829 | ||
TOTAL IMPLEMENTED | $227,960 | $386,025 |
$69,300
1,380,000
kWh
|
$145,939
-
MMBtu
|
$7,130
-
Tgal
|
$5,591 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs