ITAC Assessment: UD0754
ITAC logo
ITAC Assessment: UD0754
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Bi-Metallic Bushings and Thrust Washers
NAICS 336991: Motorcycle, Bicycle, and Parts Manufacturing
SIC 3940:
Sales Range $50
M
to 100
M
# of Employees 295
Plant Area 223,740
ft2
Annual Production 342,386,767
pieces
Production Hrs. Annual 6,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $960,916 20,010,558
kWh
Natural Gas $970,112 72,998
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $343,390 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $227,960

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $135,639 $80,000 - $135,639
-
MMBtu
- - -
02 2.4226: Use / purchase optimum sized compressor $78,829 - - - - - $78,829
03 2.7142: Utilize higher efficiency lamps and/or ballasts $74,891 $305,325 $69,300
1,380,000
kWh
- - $5,591 -
04 3.4151: Minimize water usage $17,430 $700 - $10,300
-
MMBtu
$7,130
-
Tgal
- -
05 2.6218: Turn off equipment when not in use $15,400 - $15,400
308,000
kWh
- - - -
06 2.2511: Insulate bare equipment $15,104 $5,930 $14,360
287,100
kWh
$744
-
MMBtu
- - -
07 2.2424: Use heat in flue gases to preheat products or materials $2,977 $11,246 - $2,977
-
MMBtu
- - -
08 2.2514: Cover open tanks $2,295 $355 - $2,150
-
MMBtu
$145
-
Tgal
- -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $825 $64 $825
16,500
kWh
- - - -
TOTAL RECOMMENDED $343,390 $403,620 $99,885
1,991,600
kWh
$151,810
-
MMBtu
$7,275
-
Tgal
$5,591 $78,829
TOTAL IMPLEMENTED $227,960 $386,025 $69,300
1,380,000
kWh
$145,939
-
MMBtu
$7,130
-
Tgal
$5,591 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs