ITAC Assessment: UD0747
ITAC logo
ITAC Assessment: UD0747
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Fan Systems
NAICS 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 131
Plant Area 81,600
ft2
Annual Production 897,300
pieces
Production Hrs. Annual 6,732
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $161,900 2,700,000
kWh
Natural Gas $145,800 11,640
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $281,179 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,922

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $182,400 $85,000 - - - - $182,400
02 4.625: Develop standard operating procedures $29,600 $32,000 - - - $29,600 -
03 2.2532: Use only amount of air necessary to prevent explosion hazard $23,000 $1,200 - - $23,000
-
MMBtu
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,997 $22,960 $19,132
390,456
kWh
$1,865
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,322 $14,256 $4,418
90,155
kWh
$431
-
kW-mo/yr
- - $473
06 2.2515: Use optimum thickness insulation $4,800 $9,030 - - $4,800
-
MMBtu
- -
07 2.2511: Insulate bare equipment $3,215 $1,995 $2,929
59,780
kWh
$286
-
kW-mo/yr
- - -
08 2.7261: Install timers and/or thermostats $3,095 $760 - - $3,095
-
MMBtu
- -
09 2.4231: Reduce the pressure of compressed air to the minimum required $2,678 - $2,441
49,817
kWh
$237
-
kW-mo/yr
- - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,554 $4,920 $2,273
49,397
kWh
$174
-
kW-mo/yr
- - $107
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,209 $1,800 $1,107
22,485
kWh
$102
-
kW-mo/yr
- - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $920 - $117
16,388
kWh
$803
-
kW-mo/yr
- - -
13 2.2614: Use cooling tower or economizer to replace chiller cooling $909 $1,000 $830
16,934
kWh
$79
-
kW-mo/yr
- - -
14 2.4239: Eliminate or reduce compressed air usage $480 $81 $480
9,792
kWh
- - - -
TOTAL RECOMMENDED $281,179 $175,002 $33,727
705,204
kWh
$3,977
-
kW-mo/yr
$30,895
-
MMBtu
$29,600 $182,980
TOTAL IMPLEMENTED $34,922 $46,256 $4,418
90,155
kWh
$431
-
kW-mo/yr
- $29,600 $473
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs