| Assessment Year | 2006 |
|---|---|
| Principal Product | Coated fabrics and foams |
| NAICS | 313310: Textile and Fabric Finishing Mills |
| SIC | 2295: Coated Fabrics, Not Rubberized |
| Sales Range | $100 M to 500M |
| # of Employees | 300 |
| Plant Area |
300,000
ft2
|
| Annual Production | 30,600
thousand feet
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,181,102 | 13,419,840 |
kWh
|
$0.088 |
| Electricity Demand | $532,825 | 38,341 |
kW-mo/yr
|
$13.90 |
| Electricity Fees | $9,168 | - |
|
- |
| Natural Gas | $413,073 | 46,407 |
MMBtu
|
$8.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $153,120 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $38,943 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $89,422 | $172,300 |
$(-9,495.0)
(-111,700)
kWh
|
- |
$98,917
-
MMBtu
|
|
| 02 | 2.2511: Insulate bare equipment | $20,495 | $3,700 |
$15,200
178,840
kWh
|
$5,295
-
kW-mo/yr
|
- | |
| 03 | 2.2443: Re-use or recycle hot or cold process exhaust air | $17,205 | $10,250 | - | - |
$17,205
-
MMBtu
|
|
| 04 | 2.2511: Insulate bare equipment | $10,010 | $5,280 | - | - |
$10,010
-
MMBtu
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,780 | $12,325 |
$5,780
68,000
kWh
|
- | - | |
| 06 | 2.2442: Preheat combustion air with waste heat | $4,260 | $1,190 | - | - |
$4,260
-
MMBtu
|
|
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,051 | $7,865 |
$3,051
35,900
kWh
|
- | - | |
| 08 | 2.5123: Reduce fluid flow rates | $2,270 | $600 |
$1,480
17,450
kWh
|
$790
-
kW-mo/yr
|
- | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $627 | $600 |
$627
7,374
kWh
|
- | - | |
| TOTAL RECOMMENDED | $153,120 | $214,110 |
$16,643
195,864
kWh
|
$6,085
-
kW-mo/yr
|
$130,392
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $38,943 | $36,920 |
$10,938
128,724
kWh
|
$790
-
kW-mo/yr
|
$27,215
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs