ITAC Assessment: UD0742
ITAC logo
ITAC Assessment: UD0742
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Aluminum Wheels
NAICS 331523: Nonferrous Metal Die-Casting Foundries
SIC 3363: Aluminum Die-Castings
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 300,000
ft2
Annual Production 2,500,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,436,077 46,605,942
kWh
Electricity Demand $589,925 69,552
kW-mo/yr
Natural Gas $4,769,861 470,132
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,512,062 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $503,276

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.1321: Replace fossil fuel equipment with electrical equipment $314,266 $2,000,000 $(-361,420.0)
(-7,086,670)
kWh
- $675,686
-
MMBtu
-
02 2.4224: Upgrade controls on compressors $198,228 $100,000 $198,228
3,886,817
kWh
- - -
03 2.2532: Use only amount of air necessary to prevent explosion hazard $185,439 - - - $185,439
-
MMBtu
-
04 2.5194: Redesign process $174,377 - - - $174,377
-
MMBtu
-
05 2.2414: Use waste heat from hot flue gases to preheat $157,269 $50,000 - - $157,269
-
MMBtu
-
06 2.2424: Use heat in flue gases to preheat products or materials $141,723 $50,000 - - $141,723
-
MMBtu
-
07 2.6218: Turn off equipment when not in use $67,853 - - - $67,853
-
MMBtu
-
08 2.2312: Minimize non-essential material in heat treatment process $67,500 $39,000 - - $67,500
-
MMBtu
-
09 2.1113: Reduce combustion air flow to optimum $55,855 $10,000 - - $55,855
-
MMBtu
-
10 2.2515: Use optimum thickness insulation $42,660 $15,558 - - $42,660
-
MMBtu
-
11 2.7142: Utilize higher efficiency lamps and/or ballasts $26,660 $122,500 $19,951
511,560
kWh
$6,709
-
kW-mo/yr
- -
12 2.2414: Use waste heat from hot flue gases to preheat $19,230 - - - $19,230
-
MMBtu
-
13 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,813 $51,160 $14,087
361,200
kWh
$4,726
-
kW-mo/yr
- -
14 2.4224: Upgrade controls on compressors $17,949 - $12,020
226,800
kWh
$5,929
-
kW-mo/yr
- -
15 2.4221: Install compressor air intakes in coolest locations $9,232 $5,000 $6,771
173,618
kWh
$2,461
-
kW-mo/yr
- -
16 3.1222: Reduce water use with counter current rinsing $7,083 - - - - $7,083
-
Tgal
17 2.2515: Use optimum thickness insulation $4,031 $9,057 - - $4,031
-
MMBtu
-
18 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,020 - $2,260
57,960
kWh
$760
-
kW-mo/yr
- -
19 2.7142: Utilize higher efficiency lamps and/or ballasts $874 $867 $655
16,800
kWh
$219
-
kW-mo/yr
- -
TOTAL RECOMMENDED $1,512,062 $2,453,142 $(-107,448.0)
(-1,851,915)
kWh
$20,804
-
kW-mo/yr
$1,591,623
-
MMBtu
$7,083
-
Tgal
TOTAL IMPLEMENTED $503,276 $233,367 $233,114
4,699,937
kWh
$13,617
-
kW-mo/yr
$249,462
-
MMBtu
$7,083
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs