| Assessment Year | 2006 |
|---|---|
| Principal Product | Automatic Interior Trim/Steering Wheels/Airbags |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3079: |
| Sales Range | $100 M to 500M |
| # of Employees | 700 |
| Plant Area |
465,000
ft2
|
| Annual Production | 19,700,000
units
|
| Production Hrs. Annual | 6,360
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $898,306 | 34,350,596 |
kWh
|
$0.026 |
| Electricity Demand | $838,180 | 5,466 |
kW-mo/yr
|
$153.34 |
| Natural Gas | $367,660 | 42,248 |
MMBtu
|
$8.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $367,807 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $231,267 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $65,164 | $258,960 |
$31,495
1,431,611
kWh
|
$29,551
-
kW-mo/yr
|
- | - | $4,118 | |
| 02 | 2.2622: Replace existing chiller with high efficiency model | $107,569 | $256,000 |
$54,401
2,472,768
kWh
|
$53,168
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $56,879 | $252,100 |
$7,768
356,000
kWh
|
$8,739
-
kW-mo/yr
|
- | $40,372 | - | |
| 04 | 2.2425: Use flue gases to heat process or service water | $45,101 | $17,030 | - | - |
$45,101
-
MMBtu
|
- | - | |
| 05 | 2.7134: Use photocell controls | $42,737 | - |
$3,891
176,887
kWh
|
- |
$38,846
-
MMBtu
|
- | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,847 | $52,400 |
$7,040
320,000
kWh
|
$8,807
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,352 | $2,280 |
$8,976
408,000
kWh
|
$6,376
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.2424: Use heat in flue gases to preheat products or materials | $10,428 | $10,000 |
$5,702
259,200
kWh
|
$4,726
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.6218: Turn off equipment when not in use | $3,096 | - |
$2,284
36,888
kWh
|
$812
-
kW-mo/yr
|
- | - | - | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $2,805 | $1,500 |
$989
44,954
kWh
|
$1,816
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,326 | $1,700 |
$672
30,528
kWh
|
$654
-
kW-mo/yr
|
- | - | - | |
| 12 | 2.6218: Turn off equipment when not in use | $1,280 | - |
$1,280
58,320
kWh
|
- | - | - | - | |
| 13 | 2.3511: Use plant owned transformers or lease transformers | $223 | - | - | - | - | $223 | - | |
| TOTAL RECOMMENDED | $367,807 | $851,970 |
$124,498
5,595,156
kWh
|
$114,649
-
kW-mo/yr
|
$83,947
-
MMBtu
|
$40,595 | $4,118 | ||
| TOTAL IMPLEMENTED | $231,267 | $513,580 |
$80,261
3,584,345
kWh
|
$71,565
-
kW-mo/yr
|
$38,846
-
MMBtu
|
$40,595 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs