Assessment Year | 2023 |
---|---|
Principal Product | banking services |
NAICS | 522110: Commercial Banking |
SIC | 6021: National Commercial Banks |
Sales Range | $1 M to 5M |
# of Employees | 250 |
Plant Area |
71,166
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 3,002
hrs
|
Location (State) | New Mexico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $90,520 | 1,102,560 |
kWh
|
$0.082 | |
Electricity Demand | $29,448 | 2,677 |
kW-mo/yr
|
$11.00 | |
Electricity Fees | $10,332 | - |
|
- | |
Natural Gas | $15,866 | 2,013 |
MMBtu
|
$7.88 | |
Waste Disposal Costs | |||||
Water Usage | $1,866 | 310 |
Tgal
|
$6.02 | |
TOTAL YEARLY COSTS | $148,032 | ||||
RECOMMENDED SAVINGS* | $25,902 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $16,554 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,466 | $22,203 |
$6,546
79,734
kWh
|
$2,800
-
kW-mo/yr
|
$2,120 | |
02 | 4.611: Begin a practice of predictive / preventative maintenance | $9,017 | $19,689 |
$9,017
109,829
kWh
|
- | - | |
03 | 2.7272: Install heat pipes / raise cooling setpoint | $5,088 | $71 |
$2,546
31,006
kWh
|
$2,542
-
kW-mo/yr
|
- | |
04 | 3.1161: Eliminate/reduce an operation | $331 | $50 |
$89
1,080
kWh
|
$242
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $25,902 | $42,013 |
$18,198
221,649
kWh
|
$5,584
-
kW-mo/yr
|
$2,120 | ||
TOTAL IMPLEMENTED | $16,554 | $22,274 |
$9,092
110,740
kWh
|
$5,342
-
kW-mo/yr
|
$2,120 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs