Assessment Year | 2002 |
---|---|
Principal Product | Electronic Controls |
NAICS |
n/a
|
SIC | 3625: Relays and Industrial Controls |
Sales Range | $10 M to 50M |
# of Employees | 285 |
Plant Area |
26,000
ft2
|
Annual Production | 1,600,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $139,207 | 1,056,720 |
kWh
|
$0.13 |
Natural Gas | $9,850 | 1,303 |
MMBtu
|
$7.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,772 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1171: Change product specs | $14,930 | $2,500 | - | - | - | $14,930 | |
02 | 3.1161: Eliminate/reduce an operation | $2,391 | $115 | - | - |
$2,391
-
MMBtu
|
- | |
03 | 2.2437: Recover waste heat from equipment | $997 | $102 | - | - |
$997
-
MMBtu
|
- | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $917 | $115 |
$639
7,987
kWh
|
$278
-
kW-mo/yr
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $775 | $193 |
$775
9,696
kWh
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $197 | - |
$197
2,464
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $20,207 | $3,025 |
$1,611
20,147
kWh
|
$278
-
kW-mo/yr
|
$3,388
-
MMBtu
|
$14,930 | ||
TOTAL IMPLEMENTED | $1,772 | $295 |
$775
9,696
kWh
|
- |
$997
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs