ITAC Assessment: UD0726
ITAC logo
ITAC Assessment: UD0726
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Aluminum and zinc die castings
NAICS 331523: Nonferrous Metal Die-Casting Foundries
SIC 3363: Aluminum Die-Castings
Sales Range $10
M
to 50
M
# of Employees 208
Plant Area 200,000
ft2
Annual Production 21,000,000
pieces
Production Hrs. Annual 4,050
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $332,851 8,938,455
kWh
Electricity Demand $396,931 22,596
kW-mo/yr
Natural Gas $1,110,171 118,841
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $722,726 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $410,599

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $222,216 $3,730 - - - $222,216
-
MMBtu
-
02 2.2414: Use waste heat from hot flue gases to preheat $157,981 $295,540 - - - $157,981
-
MMBtu
-
03 2.2515: Use optimum thickness insulation $113,135 $17,165 - - - $113,135
-
MMBtu
-
04 2.2414: Use waste heat from hot flue gases to preheat $93,662 $72,100 - - - $93,662
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $27,707 $93,840 $7,764
287,064
kWh
$18,422
-
kW-mo/yr
- - $1,521
06 2.7314: Reduce ventilation air $26,800 - - - - $26,800
-
MMBtu
-
07 2.2511: Insulate bare equipment $19,788 $4,000 - - - $19,788
-
MMBtu
-
08 2.2424: Use heat in flue gases to preheat products or materials $19,593 $40,000 - - - $19,593
-
MMBtu
-
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $19,470 $3,940 $6,470
239,600
kWh
$13,000
-
kW-mo/yr
- - -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,819 $12,560 $4,819
58,767
kWh
- - - -
11 2.2514: Cover open tanks $4,429 $1,200 - - - $4,429
-
MMBtu
-
12 2.4221: Install compressor air intakes in coolest locations $4,280 $736 $292
10,800
kWh
$520
-
kW-mo/yr
- $3,468
-
MMBtu
-
13 2.4224: Upgrade controls on compressors $3,679 - $1,338
49,572
kWh
$2,341
-
kW-mo/yr
- - -
14 2.4131: Size electric motors for peak operating efficiency $1,948 $500 $648
24,000
kWh
$1,300
-
kW-mo/yr
- - -
15 2.8118: Check for accuracy of utility / power meters $1,554 - - - $1,554 - -
16 2.4224: Upgrade controls on compressors $1,253 - $1,253
46,400
kWh
- - - -
17 2.7121: Utilize daylight whenever possible in lieu of artificial light $412 $960 $412
15,245
kWh
- - - -
TOTAL RECOMMENDED $722,726 $546,271 $22,996
731,448
kWh
$35,583
-
kW-mo/yr
$1,554 $661,072
-
MMBtu
$1,521
TOTAL IMPLEMENTED $410,599 $189,126 $15,878
467,848
kWh
$21,283
-
kW-mo/yr
$1,554 $370,363
-
MMBtu
$1,521
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs