ITAC Assessment: UD0700
ITAC logo
ITAC Assessment: UD0700
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Concrete accessories
NAICS 331222: Steel Wire Drawing
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area 133,485
ft2
Annual Production 3,024,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,651 2,911,200
kWh
Electricity Demand $111,729 8,484
kW-mo/yr
Natural Gas $127,272 14,968
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $779,072 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,941

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Product Savings
01 4.132: Purchase new equipment to reduce material use / cost $454,279 $226,320 $(-29,161.0)
(-1,080,000)
kWh
- $53,440
-
MMBtu
$30,000 $400,000
02 4.445: Install equipment to move product $256,000 $538,944 - - - $256,000 -
03 4.652: Replace existing equipment with more suitable substitutes $35,000 - - - - $35,000 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $12,353 $82,536 $5,670
210,000
kWh
$6,683
-
kW-mo/yr
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $6,176 $1,380 $2,835
105,000
kWh
$3,341
-
kW-mo/yr
- - -
06 2.4226: Use / purchase optimum sized compressor $2,941 - $1,350
50,000
kWh
$1,591
-
kW-mo/yr
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,656 $3,000 $2,656
45,000
kWh
- - - -
08 2.7132: Install timers on light switches in little used areas $2,312 $8,302 $1,198
44,000
kWh
$1,114
-
kW-mo/yr
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,471 $4,116 $796
25,000
kWh
$675
-
kW-mo/yr
- - -
10 2.4131: Size electric motors for peak operating efficiency $1,258 $1,405 $1,258
18,225
kWh
- - - -
11 2.4239: Eliminate or reduce compressed air usage $1,104 $700 $547
20,250
kWh
$557
-
kW-mo/yr
- - -
12 2.2414: Use waste heat from hot flue gases to preheat $850 $328 - - $850
-
MMBtu
- -
13 2.5123: Reduce fluid flow rates $774 $850 $774
11,220
kWh
- - - -
14 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $706 $243 $324
12,000
kWh
$382
-
kW-mo/yr
- - -
15 2.2511: Insulate bare equipment $604 $1,575 - - $604
-
MMBtu
- -
16 2.4224: Upgrade controls on compressors $588 $500 $270
10,000
kWh
$318
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $779,072 $870,199 $(-11,483.0)
(-529,305)
kWh
$14,661
-
kW-mo/yr
$54,894
-
MMBtu
$321,000 $400,000
TOTAL IMPLEMENTED $12,941 $83,036 $5,940
220,000
kWh
$7,001
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs