ITAC Assessment: UD0697
ITAC logo
ITAC Assessment: UD0697
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product electroplating and metal finishing
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 49
Plant Area 42,000
ft2
Annual Production 120,700
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,223 671,880
kWh
Electricity Demand $6,229 2,856
kW-mo/yr
Natural Gas $60,950 6,587
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,930 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $52,350

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $36,804 - $65,814
851,407
kWh
$7,546
-
kW-mo/yr
$(-36,556.0)
-
MMBtu
- -
02 2.8113: Purchase gas directly from a contract gas supplier $11,330 - - - - - $11,330
03 2.2514: Cover open tanks $5,579 $3,590 - - $5,245
-
MMBtu
$334
-
Tgal
-
04 2.5123: Reduce fluid flow rates $2,950 - $2,234
30,600
kWh
$716
-
kW-mo/yr
- - -
05 2.7261: Install timers and/or thermostats $2,868 $770 - - $2,868
-
MMBtu
- -
06 2.2414: Use waste heat from hot flue gases to preheat $2,816 $10,786 - - $2,816
-
MMBtu
- -
07 2.7134: Use photocell controls $2,756 $11,325 $2,081
28,506
kWh
$675
-
kW-mo/yr
- - -
08 2.1233: Analyze flue gas for proper air/fuel ratio $2,294 $100 - - $2,294
-
MMBtu
- -
09 2.1133: Adjust burners for efficient operation $1,414 $100 - - $1,414
-
MMBtu
- -
10 2.7314: Reduce ventilation air $804 - - - - - $804
11 2.2612: Use cooling tower water instead of refrigeration $782 - $23
312
kWh
- $759
-
MMBtu
- -
12 2.2612: Use cooling tower water instead of refrigeration $244 - $244
3,347
kWh
- - - -
13 2.2511: Insulate bare equipment $240 $91 - - $240
-
MMBtu
- -
14 2.4222: Install adequate dryers on air lines to eliminate blowdown $49 - $37
510
kWh
$12
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $70,930 $26,762 $70,433
914,682
kWh
$8,949
-
kW-mo/yr
$(-20,920.0)
-
MMBtu
$334
-
Tgal
$12,134
TOTAL IMPLEMENTED $52,350 $91 $68,315
885,666
kWh
$8,262
-
kW-mo/yr
$(-35,557.0)
-
MMBtu
- $11,330
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs