Assessment Year | 2004 |
---|---|
Principal Product | turbine engine components |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
250,000
ft2
|
Annual Production | 16,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $694,731 | 28,460,672 |
kWh
|
$0.024 |
Electricity Demand | $704,536 | 67,272 |
kW-mo/yr
|
$10.47 |
Natural Gas | $80,458 | 12,303 |
MMBtu
|
$6.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $858,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $356,198 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $318,395 | $324,700 |
$267,723
5,006,400
kWh
|
$50,672
-
kW-mo/yr
|
- | - | - | |
02 | 2.7229: Air condition only space necessary | $295,125 | - |
$231,190
6,533,865
kWh
|
$63,935
-
kW-mo/yr
|
- | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $117,513 | $80,244 |
$95,929
2,293,212
kWh
|
$21,584
-
kW-mo/yr
|
- | - | - | |
04 | 2.3511: Use plant owned transformers or lease transformers | $57,990 | $114,000 | - | - | $57,990 | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $33,763 | $51,348 |
$16,693
657,725
kWh
|
$17,070
-
kW-mo/yr
|
- | - | - | |
06 | 2.7314: Reduce ventilation air | $18,999 | - |
$153
6,643
kWh
|
$129
-
kW-mo/yr
|
- |
$18,717
-
MMBtu
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,530 | $5,780 |
$3,440
92,200
kWh
|
$1,090
-
kW-mo/yr
|
- | - | - | |
08 | 2.5112: Use continuous equipment which retains process heating conveyors within the heated chamber | $4,207 | $3,323 | - | - | - | - |
$4,207
-
gal
|
|
09 | 2.4224: Upgrade controls on compressors | $3,140 | - |
$1,100
48,000
kWh
|
$2,040
-
kW-mo/yr
|
- | - | - | |
10 | 2.7135: Install occupancy sensors | $1,427 | $210 |
$1,018
35,284
kWh
|
$409
-
kW-mo/yr
|
- | - | - | |
11 | 2.7231: Use radiant heater for spot heating | $883 | $1,962 | - | - | - |
$883
-
MMBtu
|
- | |
12 | 2.4221: Install compressor air intakes in coolest locations | $860 | $845 |
$300
13,200
kWh
|
$560
-
kW-mo/yr
|
- | - | - | |
13 | 2.4239: Eliminate or reduce compressed air usage | $790 | $660 |
$280
12,000
kWh
|
$510
-
kW-mo/yr
|
- | - | - | |
14 | 2.7122: Disconnect ballasts | $393 | $13 |
$155
6,720
kWh
|
$238
-
kW-mo/yr
|
- | - | - | |
15 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $288 | - |
$67
2,925
kWh
|
$221
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $858,303 | $583,085 |
$618,048
14,708,174
kWh
|
$158,458
-
kW-mo/yr
|
$57,990 |
$19,600
-
MMBtu
|
$4,207
-
gal
|
||
TOTAL IMPLEMENTED | $356,198 | $59,973 |
$252,996
7,347,362
kWh
|
$83,602
-
kW-mo/yr
|
- |
$19,600
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs