ITAC Assessment: UD0689
ITAC logo
ITAC Assessment: UD0689
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product metal stamping
NAICS 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive)
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 160,000
ft2
Annual Production 1,600,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,067 2,534,911
kWh
Electricity Demand $89,535 6,960
kW-mo/yr
Natural Gas $114,193 12,266
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $131,111 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $54,454

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.621: Use fixtures to reduce machine changeout times $28,020 $48,560 $741
23,902
kWh
- - - - $27,279 -
02 2.4312: Improve lubrication practices $20,849 $16,000 $11,616
876
kWh
$9,233
-
kW-mo/yr
- - - - -
03 4.111: Add equipment/ operators to reduce production bottleneck $20,424 - $678
21,870
kWh
- - $5,075
-
MMBtu
- $14,671 -
04 2.2414: Use waste heat from hot flue gases to preheat $16,486 $23,704 - - - $16,486
-
MMBtu
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $9,050 $27,720 $4,000
128,930
kWh
$4,930
-
kW-mo/yr
- - $380
-
lb
$(-260.0) -
06 2.8113: Purchase gas directly from a contract gas supplier $14,597 - - - - - - - $14,597
07 2.8112: Combine utility meters $3,895 $10,200 - - $3,895 - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $3,140 - $1,390
44,880
kWh
$1,750
-
kW-mo/yr
- - - - -
09 2.2437: Recover waste heat from equipment $3,082 $2,000 - - - $3,082
-
MMBtu
- - -
10 2.6218: Turn off equipment when not in use $2,425 $2,540 $2,425
78,270
kWh
- - - - - -
11 2.4224: Upgrade controls on compressors $2,285 - $1,010
32,640
kWh
$1,275
-
kW-mo/yr
- - - - -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,715 $640 $760
24,480
kWh
$955
-
kW-mo/yr
- - - - -
13 2.4231: Reduce the pressure of compressed air to the minimum required $1,680 - $820
26,440
kWh
$860
-
kW-mo/yr
- - - - -
14 2.7134: Use photocell controls $1,210 $2,040 $1,210
17,850
kWh
- - - - - -
15 2.7142: Utilize higher efficiency lamps and/or ballasts $1,012 $1,566 $455
14,689
kWh
$557
-
kW-mo/yr
- - - - -
16 2.7231: Use radiant heater for spot heating $911 $1,436 - - - $911
-
MMBtu
- - -
17 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $175 $58 $50
1,630
kWh
$125
-
kW-mo/yr
- - - - -
18 2.4231: Reduce the pressure of compressed air to the minimum required $155 - $45
1,430
kWh
$110
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $131,111 $136,464 $25,200
417,887
kWh
$19,795
-
kW-mo/yr
$3,895 $25,554
-
MMBtu
$380
-
lb
$41,690 $14,597
TOTAL IMPLEMENTED $54,454 $49,258 $4,104
132,392
kWh
$3,325
-
kW-mo/yr
- $5,075
-
MMBtu
- $41,950 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs