Assessment Year | 2004 |
---|---|
Principal Product | Coolant filtration equip. |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
130,000
ft2
|
Annual Production | 2,200,000
lb
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,647 | 1,149,140 |
kWh
|
$0.048 |
Electricity Demand | $75,156 | 5,496 |
kW-mo/yr
|
$13.67 |
Natural Gas | $51,845 | 7,508 |
MMBtu
|
$6.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,793 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,933 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $4,973 | $1,000 |
$2,617
67,109
kWh
|
$2,356
-
kW-mo/yr
|
- | - | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,400 | $1,230 | - | - |
$4,400
-
MMBtu
|
- | |
03 | 2.8114: Change rate schedules or other changes in utility service | $4,090 | - | - | - | - | $4,090 | |
04 | 3.1191: Change procedures / equipment / operating conditions | $3,420 | $9,650 |
$1,565
40,160
kWh
|
$1,855
-
kW-mo/yr
|
- | - | |
05 | 2.5111: Convert from indirect to direct fired systems | $2,740 | $540 |
$170
4,409
kWh
|
- |
$2,570
-
MMBtu
|
- | |
06 | 2.7122: Disconnect ballasts | $2,430 | $2,610 |
$1,660
42,500
kWh
|
$770
-
kW-mo/yr
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,030 | $2,350 |
$930
23,800
kWh
|
$1,100
-
kW-mo/yr
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $365 | $450 |
$165
4,250
kWh
|
$200
-
kW-mo/yr
|
- | - | |
09 | 4.821: Pay bills on time to avoid late fees | $180 | $649 |
$147
3,757
kWh
|
$33
-
kW-mo/yr
|
- | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $165 | $15 |
$75
1,910
kWh
|
$90
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $24,793 | $18,494 |
$7,329
187,895
kWh
|
$6,404
-
kW-mo/yr
|
$6,970
-
MMBtu
|
$4,090 | ||
TOTAL IMPLEMENTED | $7,933 | $4,075 |
$4,517
115,769
kWh
|
$3,416
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs