Assessment Year | 2003 |
---|---|
Principal Product | DC electric motors and injection molded parts |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
45,000
ft2
|
Annual Production | 42,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $88,496 | 2,137,200 |
kWh
|
$0.041 |
Electricity Demand | $39,503 | 5,628 |
kW-mo/yr
|
$7.02 |
Natural Gas | $33,305 | 4,467 |
MMBtu
|
$7.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,461 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,505 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $7,766 | - | - | - |
$7,766
-
MMBtu
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,363 | $14,700 |
$3,788
88,100
kWh
|
$2,575
-
kW-mo/yr
|
- | - | - | |
03 | 2.4224: Upgrade controls on compressors | $2,100 | $136 | - | - | - | - | $2,100 | |
04 | 2.4226: Use / purchase optimum sized compressor | $1,720 | - |
$1,290
30,000
kWh
|
$430
-
kW-mo/yr
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,550 | $143 |
$1,160
27,000
kWh
|
$390
-
kW-mo/yr
|
- | - | - | |
06 | 2.7122: Disconnect ballasts | $963 | $323 |
$722
16,800
kWh
|
$241
-
kW-mo/yr
|
- | - | - | |
07 | 3.4116: Meter recycled water (to reduce sewer charges) | $867 | - | - | - | - | $867 | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $815 | $218 |
$815
19,000
kWh
|
- | - | - | - | |
09 | 2.4224: Upgrade controls on compressors | $495 | - |
$495
11,500
kWh
|
- | - | - | - | |
10 | 2.7135: Install occupancy sensors | $371 | $220 |
$371
8,600
kWh
|
- | - | - | - | |
11 | 2.7131: Add area lighting switches | $264 | $640 |
$144
3,360
kWh
|
$120
-
kW-mo/yr
|
- | - | - | |
12 | 2.2511: Insulate bare equipment | $140 | - |
$97
2,250
kWh
|
$43
-
kW-mo/yr
|
- | - | - | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $47 | $3 |
$38
876
kWh
|
$9
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $23,461 | $16,383 |
$8,920
207,486
kWh
|
$3,808
-
kW-mo/yr
|
$7,766
-
MMBtu
|
$867 | $2,100 | ||
TOTAL IMPLEMENTED | $13,505 | $1,463 |
$2,879
67,036
kWh
|
$760
-
kW-mo/yr
|
$7,766
-
MMBtu
|
- | $2,100 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs