ITAC Assessment: UD0663
ITAC logo
ITAC Assessment: UD0663
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Power transmission parts and steel die forgings
NAICS 332111: Iron and Steel Forging
SIC 3462: Iron and Steel Forgings
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 195,000
ft2
Annual Production 15,000
ton
Production Hrs. Annual 2,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $380,868 12,086,400
kWh
Electricity Demand $373,251 48,060
kW-mo/yr
Electricity Fees $7,617 -
Natural Gas $1,204,244 236,191
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $284,899 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $64,670

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $82,700 $234,000 - - $82,700
-
MMBtu
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $64,670 - $32,130
1,004,000
kWh
$32,540
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $36,762 $87,200 $16,027
500,833
kWh
$20,735
-
kW-mo/yr
- -
04 2.2443: Re-use or recycle hot or cold process exhaust air $36,720 $4,800 - - $36,720
-
MMBtu
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $33,589 $102,000 $12,326
385,200
kWh
$21,263
-
kW-mo/yr
- -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $24,572 - - $40,572
-
kW-mo/yr
- $(-16,000.0)
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,728 $4,941 $1,155
36,110
kWh
$1,573
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,356 $975 $710
22,200
kWh
$646
-
kW-mo/yr
- -
09 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,042 $368 $512
16,000
kWh
$530
-
kW-mo/yr
- -
10 2.2514: Cover open tanks $760 $1,870 - - $760
-
MMBtu
-
TOTAL RECOMMENDED $284,899 $436,154 $62,860
1,964,343
kWh
$117,859
-
kW-mo/yr
$120,180
-
MMBtu
$(-16,000.0)
TOTAL IMPLEMENTED $64,670 - $32,130
1,004,000
kWh
$32,540
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs