ITAC Assessment: UD0642
ITAC logo
ITAC Assessment: UD0642
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Fluid piping system
NAICS
n/a
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 57,000
ft2
Annual Production 67,500,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $29,547 1,477,345
kWh
Electricity Demand $51,371 3,288
kW-mo/yr
Natural Gas $22,627 2,447
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $56,238 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,438

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.625: Develop standard operating procedures $39,312 - - - - $39,312 -
02 2.7145: Install skylights $8,274 $39,600 - $8,274
-
kW-mo/yr
- - -
03 3.5315: Lease / purchase baler; sell cardboard to recycler $2,876 $5,000 - - $450
-
lb
- $2,426
04 2.4226: Use / purchase optimum sized compressor $2,364 $7,000 $1,048
52,416
kWh
$1,316
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,027 $1,450 $899
44,928
kWh
$1,128
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,047 $400 $464
23,213
kWh
$583
-
kW-mo/yr
- - -
07 2.4221: Install compressor air intakes in coolest locations $338 $800 $150
7,488
kWh
$188
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $56,238 $54,250 $2,561
128,045
kWh
$11,489
-
kW-mo/yr
$450
-
lb
$39,312 $2,426
TOTAL IMPLEMENTED $5,438 $8,850 $2,411
120,557
kWh
$3,027
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs