Assessment Year | 2002 |
---|---|
Principal Product | Fluid piping system |
NAICS |
n/a
|
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
57,000
ft2
|
Annual Production | 67,500,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,547 | 1,477,345 |
kWh
|
$0.020 |
Electricity Demand | $51,371 | 3,288 |
kW-mo/yr
|
$15.62 |
Natural Gas | $22,627 | 2,447 |
MMBtu
|
$9.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $56,238 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,438 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.625: Develop standard operating procedures | $39,312 | - | - | - | - | $39,312 | - | |
02 | 2.7145: Install skylights | $8,274 | $39,600 | - |
$8,274
-
kW-mo/yr
|
- | - | - | |
03 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,876 | $5,000 | - | - |
$450
-
lb
|
- | $2,426 | |
04 | 2.4226: Use / purchase optimum sized compressor | $2,364 | $7,000 |
$1,048
52,416
kWh
|
$1,316
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,027 | $1,450 |
$899
44,928
kWh
|
$1,128
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,047 | $400 |
$464
23,213
kWh
|
$583
-
kW-mo/yr
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $338 | $800 |
$150
7,488
kWh
|
$188
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $56,238 | $54,250 |
$2,561
128,045
kWh
|
$11,489
-
kW-mo/yr
|
$450
-
lb
|
$39,312 | $2,426 | ||
TOTAL IMPLEMENTED | $5,438 | $8,850 |
$2,411
120,557
kWh
|
$3,027
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs