ITAC Assessment: UD0638
ITAC logo
ITAC Assessment: UD0638
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Aluminum electrical connectors
NAICS
n/a
SIC 3643: Current-Carrying Wiring Devices
Sales Range $50
M
to 100
M
# of Employees 230
Plant Area 113,500
ft2
Annual Production 7,000,000
lb
Production Hrs. Annual 4,820
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,124 1,845,568
kWh
Electricity Demand $48,174 5,904
kW-mo/yr
Natural Gas $18,147 1,865
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $244,650 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $204,977

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Administrative Changes Savings Increase in Production Savings
01 4.625: Develop standard operating procedures $75,000 $10,000 - - - - - - - $75,000
02 2.7142: Utilize higher efficiency lamps and/or ballasts $75,000 $17,017 - - - - - - - $75,000
03 3.1182: Make a new by-product $49,743 $30,000 $655
12,852
kWh
$1,250
-
kW-mo/yr
- - - - $47,838 -
04 3.8136: Switch to a solvent that can be cleaned and re-used $18,300 $4,175 - - - - $(-6,300.0)
-
gal
$24,600
-
gal
- -
05 3.6192: Use a less expensive method of waste removal $9,572 $21,682 - - - $(-4,456.0)
-
MMBtu
$14,028
-
gal
- - -
06 2.4113: Install motor voltage controller on lightly loaded motors $5,079 $18,900 $3,204
62,832
kWh
$1,375
-
kW-mo/yr
$500 - - - - -
07 2.2437: Recover waste heat from equipment $4,787 - - - - $4,787
-
MMBtu
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $2,144 $6,458 $1,573
30,848
kWh
$571
-
kW-mo/yr
- - - - - -
09 2.3212: Optimize plant power factor $1,935 $1,800 - - $1,935 - - - - -
10 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,751 - - $3,036
-
kW-mo/yr
- - - - $(-1,285.0) -
11 2.4221: Install compressor air intakes in coolest locations $1,211 $250 $916
17,952
kWh
$295
-
kW-mo/yr
- - - - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $128 $101 $97
1,895
kWh
$31
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $244,650 $110,383 $6,445
126,379
kWh
$6,558
-
kW-mo/yr
$2,435 $331
-
MMBtu
$7,728
-
gal
$24,600
-
gal
$46,553 $150,000
TOTAL IMPLEMENTED $204,977 $63,826 $3,241
63,547
kWh
$5,183
-
kW-mo/yr
- - - - $46,553 $150,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs