ITAC Assessment: UD0631
ITAC logo
ITAC Assessment: UD0631
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Metal stamping and welding assemblies
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 330
Plant Area 208,000
ft2
Annual Production 50,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $155,213 6,101,280
kWh
Electricity Demand $141,521 12,948
kW-mo/yr
Natural Gas $138,065 23,083
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,240,809 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,209,312

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Product Savings
01 4.445: Install equipment to move product $324,000 $1,600,000 - - - $324,000
02 4.625: Develop standard operating procedures $708,750 $350,000 - - $708,750 -
03 4.625: Develop standard operating procedures $162,000 $48,000 - - $162,000 -
04 4.514: Re-arrange equipment layout to reduce handling costs $19,834 $12,680 - - $19,834 -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,067 $7,000 $3,510
117,000
kWh
$2,557
-
kW-mo/yr
- -
06 2.6231: Utilize controls to operate equipment only when needed $9,670 $3,680 $1,800
60,000
kWh
$7,870
-
kW-mo/yr
- -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,361 $588 $1,787
59,570
kWh
$1,574
-
kW-mo/yr
- -
08 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $2,800 $960 $1,620
54,000
kWh
$1,180
-
kW-mo/yr
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,671 - $1,980
66,000
kWh
$1,443
-
kW-mo/yr
$(-1,752.0) -
10 2.3131: Reschedule plant operations or reduce load to avoid peaks $904 - - $2,304
-
kW-mo/yr
$(-1,400.0) -
11 2.6212: Turn off equipment during breaks, reduce operating time $797 $1,168 $797
26,583
kWh
- - -
12 2.4322: Use or replace with energy efficient substitutes $534 $680 $216
7,200
kWh
$318
-
kW-mo/yr
- -
13 2.6212: Turn off equipment during breaks, reduce operating time $421 $688 $421
14,025
kWh
- - -
TOTAL RECOMMENDED $1,240,809 $2,025,444 $12,131
404,378
kWh
$17,246
-
kW-mo/yr
$887,432 $324,000
TOTAL IMPLEMENTED $1,209,312 $2,003,328 $5,821
194,025
kWh
$10,493
-
kW-mo/yr
$868,998 $324,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs