ITAC Assessment: UD0596
ITAC logo
ITAC Assessment: UD0596
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product precision mechanical springs and formed wire components
NAICS
n/a
SIC 3495: Wire Springs
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 47,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 4,750
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $54,680 1,390,387
kWh
Electricity Demand $96,526 4,704
kW-mo/yr
Natural Gas $2,470 511
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,001 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,421

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $33,230 $60,000 $1,254
48,359
kWh
$13,051
-
kW-mo/yr
$(-1,075.0)
-
MMBtu
$20,000
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,200 $27,423 $2,567
125,733
kWh
$7,633
-
kW-mo/yr
- -
03 2.2437: Recover waste heat from equipment $4,221 $1,200 $412
15,826
kWh
$1,083
-
kW-mo/yr
$2,726
-
MMBtu
-
04 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $3,651 $1,298 $647
24,912
kWh
$3,004
-
kW-mo/yr
- -
05 2.7261: Install timers and/or thermostats $2,699 $3,072 $294
11,430
kWh
$2,405
-
kW-mo/yr
- -
TOTAL RECOMMENDED $54,001 $92,993 $5,174
226,260
kWh
$27,176
-
kW-mo/yr
$1,651
-
MMBtu
$20,000
TOTAL IMPLEMENTED $14,421 $28,623 $2,979
141,559
kWh
$8,716
-
kW-mo/yr
$2,726
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs