Assessment Year | 2000 |
---|---|
Principal Product | precision mechanical springs and formed wire components |
NAICS |
n/a
|
SIC | 3495: Wire Springs |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
47,000
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 4,750
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,680 | 1,390,387 |
kWh
|
$0.039 |
Electricity Demand | $96,526 | 4,704 |
kW-mo/yr
|
$20.52 |
Natural Gas | $2,470 | 511 |
MMBtu
|
$4.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $54,001 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,421 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $33,230 | $60,000 |
$1,254
48,359
kWh
|
$13,051
-
kW-mo/yr
|
$(-1,075.0)
-
MMBtu
|
$20,000 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,200 | $27,423 |
$2,567
125,733
kWh
|
$7,633
-
kW-mo/yr
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $4,221 | $1,200 |
$412
15,826
kWh
|
$1,083
-
kW-mo/yr
|
$2,726
-
MMBtu
|
- | |
04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $3,651 | $1,298 |
$647
24,912
kWh
|
$3,004
-
kW-mo/yr
|
- | - | |
05 | 2.7261: Install timers and/or thermostats | $2,699 | $3,072 |
$294
11,430
kWh
|
$2,405
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $54,001 | $92,993 |
$5,174
226,260
kWh
|
$27,176
-
kW-mo/yr
|
$1,651
-
MMBtu
|
$20,000 | ||
TOTAL IMPLEMENTED | $14,421 | $28,623 |
$2,979
141,559
kWh
|
$8,716
-
kW-mo/yr
|
$2,726
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs