ITAC Assessment: UD0582
ITAC logo
ITAC Assessment: UD0582
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product fire apparatus
NAICS
n/a
SIC 3711: Motor Vehicles and Passenger Car Bodies
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 56,000
ft2
Annual Production 48
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,989 735,346
kWh
Electricity Demand $31,850 2,772
kW-mo/yr
Natural Gas $14,676 3,086
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $167,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,817

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.446: Automate finishing process $96,632 $200,000 - - - - - $96,632 - -
02 4.122: Develop standard procedures to improve internal yields $38,800 - - - - - - $56,400 $(-41,600.0) $24,000
03 3.2123: Convert to high volume low pressure (hvlp) paint guns $19,416 $3,300 - - - - $1,416
-
lb
- - $18,000
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,601 $16,538 $2,153
79,719
kWh
$3,237
-
kW-mo/yr
- - - $211 - -
05 3.8136: Switch to a solvent that can be cleaned and re-used $5,808 $3,600 - - $5,808
-
gal
- - - - -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $1,380 $4,000 - - - $360
-
lb
- - $1,020 -
TOTAL RECOMMENDED $167,637 $227,438 $2,153
79,719
kWh
$3,237
-
kW-mo/yr
$5,808
-
gal
$360
-
lb
$1,416
-
lb
$153,243 $(-40,580.0) $42,000
TOTAL IMPLEMENTED $63,817 $19,838 $2,153
79,719
kWh
$3,237
-
kW-mo/yr
- - $1,416
-
lb
$56,611 $(-41,600.0) $42,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs