| Assessment Year | 1999 |
|---|---|
| Principal Product | fire apparatus |
| NAICS |
n/a
|
| SIC | 3711: Motor Vehicles and Passenger Car Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
56,000
ft2
|
| Annual Production | 48
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $24,989 | 735,346 |
kWh
|
$0.034 |
| Electricity Demand | $31,850 | 2,772 |
kW-mo/yr
|
$11.49 |
| Natural Gas | $14,676 | 3,086 |
MMBtu
|
$4.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $167,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,817 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.446: Automate finishing process | $96,632 | $200,000 | - | - | - | - | - | $96,632 | - | - | |
| 02 | 4.122: Develop standard procedures to improve internal yields | $38,800 | - | - | - | - | - | - | $56,400 | $(-41,600.0) | $24,000 | |
| 03 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $19,416 | $3,300 | - | - | - | - |
$1,416
-
lb
|
- | - | $18,000 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,601 | $16,538 |
$2,153
79,719
kWh
|
$3,237
-
kW-mo/yr
|
- | - | - | $211 | - | - | |
| 05 | 3.8136: Switch to a solvent that can be cleaned and re-used | $5,808 | $3,600 | - | - |
$5,808
-
gal
|
- | - | - | - | - | |
| 06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,380 | $4,000 | - | - | - |
$360
-
lb
|
- | - | $1,020 | - | |
| TOTAL RECOMMENDED | $167,637 | $227,438 |
$2,153
79,719
kWh
|
$3,237
-
kW-mo/yr
|
$5,808
-
gal
|
$360
-
lb
|
$1,416
-
lb
|
$153,243 | $(-40,580.0) | $42,000 | ||
| TOTAL IMPLEMENTED | $63,817 | $19,838 |
$2,153
79,719
kWh
|
$3,237
-
kW-mo/yr
|
- | - |
$1,416
-
lb
|
$56,611 | $(-41,600.0) | $42,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs