Assessment Year | 2008 |
---|---|
Principal Product | Pharmaceutical Medication |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 143 |
Plant Area |
1,000,000
ft2
|
Annual Production | 100,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,447,109 | 17,041,200 |
kWh
|
$0.14 |
Electricity Demand | $227,658 | 27,989 |
kW-mo/yr
|
$8.13 |
Electricity Fees | $20,151 | - |
|
- |
Fuel Oil #6 | $2,018,471 | 104,310 |
MMBtu
|
$19.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,418,768 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $195,738 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2423: Install waste heat boiler to produce steam | $1,069,901 | $2,000,000 |
$479,531
3,339,353
kWh
|
$38,829
-
kW-mo/yr
|
$551,541
-
MMBtu
|
- | |
02 | 3.2161: Closely monitor chemical additions to increase bath life | $98,398 | $18,460 | - | - | - | $98,398 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $86,183 | $45,980 |
$79,851
556,064
kWh
|
$6,332
-
kW-mo/yr
|
- | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $73,832 | $1,750 | - | - |
$73,832
-
MMBtu
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $61,527 | $56,000 | - | - |
$61,527
-
MMBtu
|
- | |
06 | 2.2113: Repair or replace steam traps | $11,109 | $400 | - | - |
$11,109
-
MMBtu
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,769 | $1,210 |
$8,105
56,442
kWh
|
$664
-
kW-mo/yr
|
- | - | |
08 | 2.4323: Use optimum size and capacity equipment | $5,419 | $4,800 |
$5,001
34,828
kWh
|
$418
-
kW-mo/yr
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,630 | $40 |
$3,350
23,331
kWh
|
$280
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $1,418,768 | $2,128,640 |
$575,838
4,010,018
kWh
|
$46,523
-
kW-mo/yr
|
$698,009
-
MMBtu
|
$98,398 | ||
TOTAL IMPLEMENTED | $195,738 | $21,860 |
$11,455
79,773
kWh
|
$944
-
kW-mo/yr
|
$84,941
-
MMBtu
|
$98,398 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs