| Assessment Year | 1999 |
|---|---|
| Principal Product | automotive and industrial batteries |
| NAICS |
n/a
|
| SIC | 3692: Primary Batteries, Dry and Wet |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
174,000
ft2
|
| Annual Production | 3,920,600
pieces
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $380,222 | 17,861,372 |
kWh
|
$0.021 |
| Electricity Demand | $359,190 | 34,176 |
kW-mo/yr
|
$10.51 |
| Natural Gas | $165,384 | 38,672 |
MMBtu
|
$4.28 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $559,254 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,784 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.446: Automate finishing process | $270,000 | $150,000 | - | $270,000 | - | - | - | |
| 02 | 3.3128: Utilize other methods to remove contaminants | $269,087 | $365,000 | - | $(-60,000.0) | $(-153,600.0) | - | $482,687 | |
| 03 | 3.4116: Meter recycled water (to reduce sewer charges) | $10,377 | $4,700 | - | - | $10,377 | - | - | |
| 04 | 3.1163: Use plastic pallets instead of wood | $6,058 | $21,000 | - | - | - | $6,058 | - | |
| 05 | 3.3122: Use filtration, centrifuging to remove contaminants | $2,325 | $9,165 |
$2,925
-
Tgal
|
$(-600.0) | - | - | - | |
| 06 | 3.4153: Use counter current rinsing to reduce waste water | $1,407 | $1,000 |
$1,407
-
Tgal
|
- | - | - | - | |
| TOTAL RECOMMENDED | $559,254 | $550,865 |
$4,332
-
Tgal
|
$209,400 | $(-143,223.0) | $6,058 | $482,687 | ||
| TOTAL IMPLEMENTED | $11,784 | $5,700 |
$1,407
-
Tgal
|
- | $10,377 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs