| Assessment Year | 1999 |
|---|---|
| Principal Product | Metalworking lathes and repair parts |
| NAICS |
n/a
|
| SIC | 3541: Machine Tools, Metal Cutting Types |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
135,000
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $92,956 | 2,021,395 |
kWh
|
$0.046 |
| Electricity Demand | $96,033 | 6,806 |
kW-mo/yr
|
$14.11 |
| Natural Gas | $31,413 | 6,557 |
MMBtu
|
$4.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $125,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,984 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $100,000 | $200,000 | - | - | - | - | - | - | $100,000 | |
| 02 | 2.3137: Use power during off-peak periods | $12,265 | $5,000 | - | - | $12,265 | - | - | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $5,566 | $8,140 |
$1,214
57,737
kWh
|
$4,352
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,418 | $14,216 |
$1,071
50,996
kWh
|
$3,347
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $1,139 | $3,000 | - | - | - |
$479
-
gal
|
- | $660 | - | |
| 06 | 3.5121: Recycle waste ink and cleanup solvent | $942 | $3,000 | - | - | - | - |
$297
-
gal
|
$645 | - | |
| 07 | 2.7131: Add area lighting switches | $877 | - |
$191
9,086
kWh
|
$686
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $125,207 | $233,356 |
$2,476
117,819
kWh
|
$8,385
-
kW-mo/yr
|
$12,265 |
$479
-
gal
|
$297
-
gal
|
$1,305 | $100,000 | ||
| TOTAL IMPLEMENTED | $9,984 | $22,356 |
$2,285
108,733
kWh
|
$7,699
-
kW-mo/yr
|
- | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs