Assessment Year | 1998 |
---|---|
Principal Product | Enviromental systems, continuous emissions monitoring system |
NAICS |
n/a
|
SIC | 3625: Relays and Industrial Controls |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
93,900
ft2
|
Annual Production | 3,575
Tgal
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,643 | 2,750,293 |
kWh
|
$0.044 |
Electricity Demand | $22,901 | 6,240 |
kW-mo/yr
|
$3.67 |
Natural Gas | $19,135 | 3,271 |
MMBtu
|
$5.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,854 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,786 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $18,790 | $8,000 |
$17,595
423,212
kWh
|
$1,195
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,343 | $45,360 |
$8,212
195,487
kWh
|
$3,131
-
kW-mo/yr
|
- | - | - | |
03 | 2.7233: Use properly designed and sized hvac equipment | $7,068 | $7,600 |
$5,110
122,802
kWh
|
$559
-
kW-mo/yr
|
- |
$299
-
Tgal
|
$1,100 | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $1,453 | $8,000 |
$1,658
39,859
kWh
|
$415
-
kW-mo/yr
|
$(-620.0)
-
MMBtu
|
- | - | |
05 | 3.6192: Use a less expensive method of waste removal | $1,200 | - | - | - | - | - | $1,200 | |
TOTAL RECOMMENDED | $39,854 | $68,960 |
$32,575
781,360
kWh
|
$5,300
-
kW-mo/yr
|
$(-620.0)
-
MMBtu
|
$299
-
Tgal
|
$2,300 | ||
TOTAL IMPLEMENTED | $32,786 | $61,360 |
$27,465
658,558
kWh
|
$4,741
-
kW-mo/yr
|
$(-620.0)
-
MMBtu
|
- | $1,200 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs