ITAC Assessment: UD0558
ITAC logo
ITAC Assessment: UD0558
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Enviromental systems, continuous emissions monitoring system
NAICS
n/a
SIC 3625: Relays and Industrial Controls
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 93,900
ft2
Annual Production 3,575
Tgal
Production Hrs. Annual 4,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $120,643 2,750,293
kWh
Electricity Demand $22,901 6,240
kW-mo/yr
Natural Gas $19,135 3,271
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,854 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,786

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.4226: Use / purchase optimum sized compressor $18,790 $8,000 $17,595
423,212
kWh
$1,195
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,343 $45,360 $8,212
195,487
kWh
$3,131
-
kW-mo/yr
- - -
03 2.7233: Use properly designed and sized hvac equipment $7,068 $7,600 $5,110
122,802
kWh
$559
-
kW-mo/yr
- $299
-
Tgal
$1,100
04 2.7232: Replace existing hvac unit with high efficiency model $1,453 $8,000 $1,658
39,859
kWh
$415
-
kW-mo/yr
$(-620.0)
-
MMBtu
- -
05 3.6192: Use a less expensive method of waste removal $1,200 - - - - - $1,200
TOTAL RECOMMENDED $39,854 $68,960 $32,575
781,360
kWh
$5,300
-
kW-mo/yr
$(-620.0)
-
MMBtu
$299
-
Tgal
$2,300
TOTAL IMPLEMENTED $32,786 $61,360 $27,465
658,558
kWh
$4,741
-
kW-mo/yr
$(-620.0)
-
MMBtu
- $1,200
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs