Assessment Year | 1998 |
---|---|
Principal Product | Corrugated boxes and shipping containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
175,000
ft2
|
Annual Production | 66,000
ton
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $96,797 | 4,762,310 |
kWh
|
$0.020 |
Electricity Demand | $156,812 | 10,176 |
kW-mo/yr
|
$15.41 |
Natural Gas | $225,791 | 63,672 |
MMBtu
|
$3.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $227,563 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $227,563 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.122: Develop standard procedures to improve internal yields | $189,046 | - | - | - | - | - | $2,700 | $4,538 | $762 | $181,046 | |
02 | 3.5316: Contract a wood pallet recycling company | $19,800 | - | - | - | - | - | - | $19,800 | - | - | |
03 | 2.1133: Adjust burners for efficient operation | $8,037 | $200 | - | - |
$8,037
-
MMBtu
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,225 | $11,147 |
$1,381
65,944
kWh
|
$1,844
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,784 | - |
$1,193
56,858
kWh
|
$1,591
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $2,459 | - | - | - | - |
$2,459
-
Tgal
|
- | - | - | - | |
07 | 2.3212: Optimize plant power factor | $1,680 | $2,250 | - |
$1,680
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $532 | $200 |
$532
25,205
kWh
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $227,563 | $13,797 |
$3,106
148,007
kWh
|
$5,115
-
kW-mo/yr
|
$8,037
-
MMBtu
|
$2,459
-
Tgal
|
$2,700 | $24,338 | $762 | $181,046 | ||
TOTAL IMPLEMENTED | $227,563 | $13,797 |
$3,106
148,007
kWh
|
$5,115
-
kW-mo/yr
|
$8,037
-
MMBtu
|
$2,459
-
Tgal
|
$2,700 | $24,338 | $762 | $181,046 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs