| Assessment Year | 1998 |
|---|---|
| Principal Product | Distilled & rectified liquors and bottling of blended liquor |
| NAICS |
n/a
|
| SIC | 2085: Distilled and Blended Liquors |
| Sales Range | $100 M to 500M |
| # of Employees | 250 |
| Plant Area |
198,000
ft2
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,398 | 3,353,458 |
kWh
|
$0.021 |
| Electricity Demand | $149,365 | 10,416 |
kW-mo/yr
|
$14.34 |
| Natural Gas | $159,390 | 37,950 |
MMBtu
|
$4.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $86,971 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,271 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.7212: Improved material handling (mixing and transfer) | $21,875 | $500 | - | - | - |
$21,875
-
lb
|
- | - | |
| 02 | 2.2136: Install / repair insulation on steam lines | $14,410 | $12,100 | - | - |
$14,410
-
MMBtu
|
- | - | - | |
| 03 | 3.1163: Use plastic pallets instead of wood | $5,600 | - | - | - | - | - | $5,600 | - | |
| 04 | 2.4225: Install common header on compressors | $12,000 | $2,000 |
$2,567
123,974
kWh
|
$6,023
-
kW-mo/yr
|
- | - | $1,065 |
$2,345
-
Tgal
|
|
| 05 | 2.7241: Install outside air damper / economizer on hvac unit | $11,947 | $10,000 |
$11,715
195,193
kWh
|
- |
$232
-
MMBtu
|
- | - | - | |
| 06 | 2.6213: Turn off steam / hot water lines leading to space heating units | $8,274 | $1,000 | - | - |
$8,274
-
MMBtu
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,594 | $13,677 |
$5,622
271,688
kWh
|
$1,972
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.4224: Upgrade controls on compressors | $5,271 | $800 | - | - | - | - | - |
$5,271
-
Tgal
|
|
| TOTAL RECOMMENDED | $86,971 | $40,077 |
$19,904
590,855
kWh
|
$7,995
-
kW-mo/yr
|
$22,916
-
MMBtu
|
$21,875
-
lb
|
$6,665 |
$7,616
-
Tgal
|
||
| TOTAL IMPLEMENTED | $5,271 | $800 | - | - | - | - | - |
$5,271
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs