| Assessment Year | 1996 |
|---|---|
| Principal Product | Metal Closures |
| NAICS |
n/a
|
| SIC | 3466: Crowns and Closures |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
50,000
ft2
|
| Annual Production | 1,500,000,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $462,494 | 7,504,983 |
kWh
|
$0.062 |
| Electricity Demand | $187,986 | 14,979 |
kW-mo/yr
|
$12.55 |
| Natural Gas | $369,308 | 147,599 |
MMBtu
|
$2.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $54,380 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $4,092 | $2,932 |
$3,065
49,824
kWh
|
$1,027
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,724 | $17,620 |
$3,762
60,961
kWh
|
$1,962
-
kW-mo/yr
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $10,473 | $12,145 |
$8,413
136,577
kWh
|
$2,060
-
kW-mo/yr
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $22,161 | $8,797 |
$18,561
179,367
kWh
|
$3,600
-
kW-mo/yr
|
- | |
| 05 | 2.4314: Use synthetic lubricant | $8,134 | $3,201 |
$6,132
19,050
kWh
|
$2,002
-
kW-mo/yr
|
- | |
| 06 | 2.6218: Turn off equipment when not in use | $304 | - |
$184
2,931
kWh
|
$120
-
kW-mo/yr
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $612 | - |
$526
8,499
kWh
|
$86
-
kW-mo/yr
|
- | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,880 | - | - | - |
$2,880
-
lb
|
|
| TOTAL RECOMMENDED | $54,380 | $44,695 |
$40,643
457,209
kWh
|
$10,857
-
kW-mo/yr
|
$2,880
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs