Assessment Year | 1998 |
---|---|
Principal Product | Aluminum & Cast Iron Automotive Parts |
NAICS |
n/a
|
SIC | 3365: Aluminum Foundries |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
100,000
ft2
|
Annual Production | 8,000,000
pieces
|
Production Hrs. Annual | 7,800
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $225,815 | 10,604,631 |
kWh
|
$0.021 |
Electricity Demand | $271,102 | 19,560 |
kW-mo/yr
|
$13.86 |
Natural Gas | $24,786 | 5,545 |
MMBtu
|
$4.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $266,102 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $213,299 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 3.7391: Implement a maintenance program to keep racks and tanks free of rust, cracks, or corrosion | $211,528 | $50,000 | - | - | $211,528 | |
02 | 4.423: Move product using mechanical means | $44,426 | $3,000 | - | - | $44,426 | |
03 | 2.4226: Use / purchase optimum sized compressor | $8,377 | $(-10,000.0) |
$3,655
171,747
kWh
|
$3,722
-
kW-mo/yr
|
$1,000 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,771 | $5,737 |
$668
31,360
kWh
|
$1,103
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $266,102 | $48,737 |
$4,323
203,107
kWh
|
$4,825
-
kW-mo/yr
|
$256,954 | ||
TOTAL IMPLEMENTED | $213,299 | $55,737 |
$668
31,360
kWh
|
$1,103
-
kW-mo/yr
|
$211,528 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs