ITAC Assessment: UD0538
ITAC logo
ITAC Assessment: UD0538
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Aluminum & Cast Iron Automotive Parts
NAICS
n/a
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 100,000
ft2
Annual Production 8,000,000
pieces
Production Hrs. Annual 7,800
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $225,815 10,604,631
kWh
Electricity Demand $271,102 19,560
kW-mo/yr
Natural Gas $24,786 5,545
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $266,102 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $213,299

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 3.7391: Implement a maintenance program to keep racks and tanks free of rust, cracks, or corrosion $211,528 $50,000 - - $211,528
02 4.423: Move product using mechanical means $44,426 $3,000 - - $44,426
03 2.4226: Use / purchase optimum sized compressor $8,377 $(-10,000.0) $3,655
171,747
kWh
$3,722
-
kW-mo/yr
$1,000
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,771 $5,737 $668
31,360
kWh
$1,103
-
kW-mo/yr
-
TOTAL RECOMMENDED $266,102 $48,737 $4,323
203,107
kWh
$4,825
-
kW-mo/yr
$256,954
TOTAL IMPLEMENTED $213,299 $55,737 $668
31,360
kWh
$1,103
-
kW-mo/yr
$211,528
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs