ITAC Assessment: UD0523
ITAC logo
ITAC Assessment: UD0523
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Fabricated Rubber Products, Base boards, floor tile
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 300,000
ft2
Annual Production 0
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,262 3,863,130
kWh
Electricity Demand $133,862 11,520
kW-mo/yr
Natural Gas $304,823 83,633
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $259,146 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $238,573

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $34,683 - - $32,629
-
kW-mo/yr
$3,614
-
MMBtu
- $(-1,560.0)
02 3.1172: Revise raw material specs $203,890 $100,000 - - - $203,890
-
gal
-
03 2.4221: Install compressor air intakes in coolest locations $4,766 $4,000 $422
19,930
kWh
- $4,344
-
MMBtu
- -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,323 - - $11,155
-
kW-mo/yr
- - $(-832.0)
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,484 $16,515 $2,373
111,372
kWh
$3,111
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $259,146 $120,515 $2,795
131,302
kWh
$46,895
-
kW-mo/yr
$7,958
-
MMBtu
$203,890
-
gal
$(-2,392.0)
TOTAL IMPLEMENTED $238,573 $100,000 - $32,629
-
kW-mo/yr
$3,614
-
MMBtu
$203,890
-
gal
$(-1,560.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs