ITAC Assessment: UD0521
ITAC logo
ITAC Assessment: UD0521
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product inflatable bladders
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area 22,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,070 622,509
kWh
Electricity Demand $12,768 912
kW-mo/yr
Electricity Fees $266 -
Natural Gas $4,209 829
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,475 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,720

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3191: Use demand controller or load shedder $7,099 - - $7,099
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $630 $100 $630
19,637
kWh
- -
03 2.4221: Install compressor air intakes in coolest locations $868 $1,000 $128
4,103
kWh
- $740
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $657 $1,764 $179
8,499
kWh
$478
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,098 $2,828 $518
15,826
kWh
$580
-
kW-mo/yr
-
06 2.4321: Upgrade obsolete equipment $1,123 $1,000 $518
16,120
kWh
$605
-
kW-mo/yr
-
TOTAL RECOMMENDED $11,475 $6,692 $1,973
64,185
kWh
$8,762
-
kW-mo/yr
$740
-
MMBtu
TOTAL IMPLEMENTED $9,720 $2,100 $1,276
39,860
kWh
$7,704
-
kW-mo/yr
$740
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs