Assessment Year | 1997 |
---|---|
Principal Product | inflatable bladders |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
22,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $13,070 | 622,509 |
kWh
|
$0.021 |
Electricity Demand | $12,768 | 912 |
kW-mo/yr
|
$14.00 |
Electricity Fees | $266 | - |
|
- |
Natural Gas | $4,209 | 829 |
MMBtu
|
$5.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,475 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,720 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $7,099 | - | - |
$7,099
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $630 | $100 |
$630
19,637
kWh
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $868 | $1,000 |
$128
4,103
kWh
|
- |
$740
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $657 | $1,764 |
$179
8,499
kWh
|
$478
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,098 | $2,828 |
$518
15,826
kWh
|
$580
-
kW-mo/yr
|
- | |
06 | 2.4321: Upgrade obsolete equipment | $1,123 | $1,000 |
$518
16,120
kWh
|
$605
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $11,475 | $6,692 |
$1,973
64,185
kWh
|
$8,762
-
kW-mo/yr
|
$740
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,720 | $2,100 |
$1,276
39,860
kWh
|
$7,704
-
kW-mo/yr
|
$740
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs