ITAC Assessment: UD0510
ITAC logo
ITAC Assessment: UD0510
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Injection molded plastics
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 55,000
ft2
Annual Production 9,500,000
pieces
Production Hrs. Annual 7,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $116,938 5,570,047
kWh
Electricity Demand $172,892 12,288
kW-mo/yr
Electricity Fees $2,926 -
Natural Gas $13,389 2,726
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,662 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,965

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (haz) Savings
01 2.3212: Optimize plant power factor $2,926 $5,000 - $2,926
-
kW-mo/yr
- -
02 3.4114: Replace city water with recycled water via cooling tower $4,651 $500 - - $4,651
-
Tgal
-
03 2.4226: Use / purchase optimum sized compressor $11,314 $1,000 $6,586
313,599
kWh
$4,728
-
kW-mo/yr
- -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,641 - - - - $3,641
-
lb
05 2.7142: Utilize higher efficiency lamps and/or ballasts $11,774 $33,595 $3,722
177,022
kWh
$8,052
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $356 $910 $119
5,569
kWh
$237
-
kW-mo/yr
- -
TOTAL RECOMMENDED $34,662 $41,005 $10,427
496,190
kWh
$15,943
-
kW-mo/yr
$4,651
-
Tgal
$3,641
-
lb
TOTAL IMPLEMENTED $15,965 $1,500 $6,586
313,599
kWh
$4,728
-
kW-mo/yr
$4,651
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs