Assessment Year | 1996 |
---|---|
Principal Product | folding cartons |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 89 |
Plant Area |
188,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,355 | 3,818,582 |
kWh
|
$0.030 |
Electricity Demand | $101,948 | 9,444 |
kW-mo/yr
|
$10.80 |
Natural Gas | $33,634 | 7,090 |
MMBtu
|
$4.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,819 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,396 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $12,517 | $14,000 |
$5,607
264,947
kWh
|
$4,994
-
kW-mo/yr
|
- | - | - | - | $1,916 | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,890 | - | - |
$8,610
-
kW-mo/yr
|
- | - | $(-720.0) | - | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $12,533 | - |
$4,935
186,108
kWh
|
$3,368
-
kW-mo/yr
|
$4,230
-
MMBtu
|
- | - | - | - | |
04 | 2.7122: Disconnect ballasts | $1,437 | $1,650 |
$664
31,653
kWh
|
$641
-
kW-mo/yr
|
- | - | - | $132 | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,632 | $12,454 |
$2,696
128,370
kWh
|
$3,936
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 3.5121: Recycle waste ink and cleanup solvent | $810 | - | - | - | - |
$810
-
gal
|
- | - | - | |
TOTAL RECOMMENDED | $41,819 | $28,104 |
$13,902
611,078
kWh
|
$21,549
-
kW-mo/yr
|
$4,230
-
MMBtu
|
$810
-
gal
|
$(-720.0) | $132 | $1,916 | ||
TOTAL IMPLEMENTED | $21,396 | $28,104 |
$8,967
424,970
kWh
|
$9,571
-
kW-mo/yr
|
- |
$810
-
gal
|
- | $132 | $1,916 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs