ITAC Assessment: UD0482
ITAC logo
ITAC Assessment: UD0482
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product deep drawn metal stampings
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 97,000
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $88,457 2,737,397
kWh
Electricity Demand $103,177 8,520
kW-mo/yr
Natural Gas $37,734 7,925
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,913 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,827

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Administrative Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $40,000 $20,000 $9,597
457,210
kWh
$42,295
-
kW-mo/yr
$(-11,524.0)
-
MMBtu
- $(-368.0)
02 2.3212: Optimize plant power factor $5,827 $3,000 - $5,827
-
kW-mo/yr
- - -
03 3.4116: Meter recycled water (to reduce sewer charges) $40,000 $10,000 - - - $40,000
-
gal
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,329 $7,021 $946
45,135
kWh
$2,383
-
kW-mo/yr
- - -
05 2.4224: Upgrade controls on compressors $12,397 $500 $6,006
286,049
kWh
$6,391
-
kW-mo/yr
- - -
06 2.4133: Use most efficient type of electric motors $1,360 $310 $420
19,930
kWh
$940
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $102,913 $40,831 $16,969
808,324
kWh
$57,836
-
kW-mo/yr
$(-11,524.0)
-
MMBtu
$40,000
-
gal
$(-368.0)
TOTAL IMPLEMENTED $45,827 $23,000 $9,597
457,210
kWh
$48,122
-
kW-mo/yr
$(-11,524.0)
-
MMBtu
- $(-368.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs