ITAC Assessment: UD0475
ITAC logo
ITAC Assessment: UD0475
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product rubber footwear
NAICS
n/a
SIC 3021: Rubber and Plastics Footwear
Sales Range $10
M
to 50
M
# of Employees 78
Plant Area 146,000
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 7,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $253,900 4,793,376
kWh
Natural Gas $155,955 40,581
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $219,819 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $13,500 $5,000 - - - $13,500
02 2.4226: Use / purchase optimum sized compressor $5,945 - $5,070
112,544
kWh
- - $875
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $8,535 $4,300 $10,519
150,059
kWh
$(-1,984.0)
-
MMBtu
- -
04 2.2437: Recover waste heat from equipment $8,114 $8,000 $8,114
135,111
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $6,440 $10,410 $6,440
67,702
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $9,260 $16,682 $10,501
202,814
kWh
$(-1,241.0)
-
MMBtu
- -
07 2.5193: Convert from batch to continuous operation $168,025 $200,000 $18,025
271,688
kWh
- $140,000 $10,000
TOTAL RECOMMENDED $219,819 $244,392 $58,669
939,918
kWh
$(-3,225.0)
-
MMBtu
$140,000 $24,375
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs