ITAC Assessment: UD0450
ITAC logo
ITAC Assessment: UD0450
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product condiments
NAICS
n/a
SIC 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings
Sales Range $50
M
to 100
M
# of Employees 350
Plant Area 132,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $260,428 4,646,835
kWh
Natural Gas $85,771 16,224
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $115,603 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $81,061

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Water Disposal Savings Administrative Changes Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $9,163 - $6,963
320,047
kWh
- - - $2,200
02 2.2437: Recover waste heat from equipment $4,096 $2,000 - $4,096
-
MMBtu
- - -
03 2.6231: Utilize controls to operate equipment only when needed $6,103 $2,000 $5,645
138,628
kWh
- - - $458
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,449 $10,000 $6,084
92,907
kWh
$(-635.0)
-
MMBtu
- - -
05 2.7111: Reduce illumination to minimum necessary levels $980 $250 $1,117
51,290
kWh
$(-438.0)
-
MMBtu
- - $301
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,370 $2,500 $2,401
24,033
kWh
- $(-1,031.0)
-
MMBtu
- -
07 3.4155: Meter waste water $61,699 $2,000 - - - - $61,699
08 3.7122: Maximize production runs to reduce cleaning $24,424 - - $6,000
-
MMBtu
- $18,424
-
Tgal
-
09 2.6231: Utilize controls to operate equipment only when needed $2,319 - $2,319
106,682
kWh
- - - -
TOTAL RECOMMENDED $115,603 $18,750 $24,529
733,587
kWh
$9,023
-
MMBtu
$(-1,031.0)
-
MMBtu
$18,424
-
Tgal
$64,658
TOTAL IMPLEMENTED $81,061 $6,000 $12,608
458,675
kWh
$4,096
-
MMBtu
- - $64,357
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs