ITAC Assessment: UD0434
ITAC logo
ITAC Assessment: UD0434
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product fluid dairy and juice products
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $50
M
to 100
M
# of Employees 85
Plant Area 30,000
ft2
Annual Production 31,000
Tgal
Production Hrs. Annual 7,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $351,385 6,549,531
kWh
Natural Gas $73,778 13,588
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,923 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,923

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings Water Consumption Savings
01 2.3212: Optimize plant power factor $4,831 $8,000 $4,831
-
kWh
- -
02 3.4114: Replace city water with recycled water via cooling tower $14,462 $7,500 $(-1,765.0)
(-29,894)
kWh
$(-500.0) $16,727
-
Tgal
03 2.3137: Use power during off-peak periods $13,081 - $13,081
-
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,504 $12,960 $4,504
70,633
kWh
- -
05 2.6231: Utilize controls to operate equipment only when needed $2,045 $300 $2,045
96,424
kWh
- -
TOTAL RECOMMENDED $38,923 $28,760 $22,696
137,163
kWh
$(-500.0) $16,727
-
Tgal
TOTAL IMPLEMENTED $38,923 $28,760 $22,696
137,163
kWh
$(-500.0) $16,727
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs