ITAC Assessment: UD0409
ITAC logo
ITAC Assessment: UD0409
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product mirrors
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $1
M
to 5
M
# of Employees 21
Plant Area 25,000
ft2
Annual Production 3,000
thousand feet
Production Hrs. Annual 2,625
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $43,524 453,107
kWh
Natural Gas $9,050 1,903
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,699 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,927

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,772 - $3,964
-
kWh
$(-192.0)
-
MMBtu
02 2.7111: Reduce illumination to minimum necessary levels $676 $2,471 $816
12,896
kWh
$(-140.0)
-
MMBtu
03 2.7261: Install timers and/or thermostats $1,251 $450 - $1,251
-
MMBtu
TOTAL RECOMMENDED $5,699 $2,921 $4,780
12,896
kWh
$919
-
MMBtu
TOTAL IMPLEMENTED $1,927 $2,921 $816
12,896
kWh
$1,111
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs