Assessment Year | 1993 |
---|---|
Principal Product | mirrors |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $1 M to 5M |
# of Employees | 21 |
Plant Area |
25,000
ft2
|
Annual Production | 3,000
thousand feet
|
Production Hrs. Annual | 2,625
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,524 | 453,107 |
kWh
|
$0.096 |
Natural Gas | $9,050 | 1,903 |
MMBtu
|
$4.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,699 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,927 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,772 | - |
$3,964
-
kWh
|
$(-192.0)
-
MMBtu
|
|
02 | 2.7111: Reduce illumination to minimum necessary levels | $676 | $2,471 |
$816
12,896
kWh
|
$(-140.0)
-
MMBtu
|
|
03 | 2.7261: Install timers and/or thermostats | $1,251 | $450 | - |
$1,251
-
MMBtu
|
|
TOTAL RECOMMENDED | $5,699 | $2,921 |
$4,780
12,896
kWh
|
$919
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,927 | $2,921 |
$816
12,896
kWh
|
$1,111
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs