| Assessment Year | 1993 |
|---|---|
| Principal Product | printed circuit boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 112 |
| Plant Area |
56,000
ft2
|
| Annual Production | 10,900,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $199,710 | 4,284,584 |
kWh
|
$0.047 |
| Natural Gas | $28,188 | 7,316 |
MMBtu
|
$3.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,389 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $36,825 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,502 | - |
$10,502
-
kWh
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,564 | - |
$2,564
-
kWh
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $1,064 | - | - |
$1,064
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $4,680 | $1,500 | - |
$4,680
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,502 | $25,812 |
$12,502
221,278
kWh
|
- | |
| 06 | 2.3191: Use demand controller or load shedder | $5,782 | $15,000 |
$5,782
-
kWh
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $2,295 | $1,350 |
$353
16,413
kWh
|
$1,942
-
MMBtu
|
|
| TOTAL RECOMMENDED | $39,389 | $43,662 |
$31,703
237,691
kWh
|
$7,686
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $36,825 | $43,662 |
$29,139
237,691
kWh
|
$7,686
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs