| Assessment Year | 1992 |
|---|---|
| Principal Product | INJECTION-MOLDED PLASTIC |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 12,000,000
pieces
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $584,734 | 13,381,008 |
kWh
|
$0.044 |
| Natural Gas | $77,446 | 21,197 |
MMBtu
|
$3.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $37,315 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,194 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,478 | - |
$2,478
-
kWh
|
|
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $14,160 | - |
$14,160
-
kWh
|
|
| 03 | 2.6232: Install set-back timers | $556 | - |
$556
25,498
kWh
|
|
| 04 | 2.6232: Install set-back timers | $7,731 | - |
$7,731
193,728
kWh
|
|
| 05 | 2.3191: Use demand controller or load shedder | $12,390 | $30,000 |
$12,390
-
kWh
|
|
| TOTAL RECOMMENDED | $37,315 | $30,000 |
$37,315
219,226
kWh
|
||
| TOTAL IMPLEMENTED | $17,194 | - |
$17,194
25,498
kWh
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs