| Assessment Year | 1992 |
|---|---|
| Principal Product | FLEX. METALLIC CONDUIT |
| NAICS |
n/a
|
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $5 M to 10M |
| # of Employees | 65 |
| Plant Area |
n/a
|
| Annual Production | 75,000
thousand feet
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $168,855 | 1,261,430 |
kWh
|
$0.13 |
| Natural Gas | $21,028 | 4,404 |
MMBtu
|
$4.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,549 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,610 | - |
$6,610
-
kWh
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $9,979 | - |
$10,918
75,615
kWh
|
$(-939.0)
-
MMBtu
|
|
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,241 | - |
$3,577
15,826
kWh
|
$(-336.0)
-
MMBtu
|
|
| 04 | 2.6232: Install set-back timers | $275 | - |
$368
9,379
kWh
|
$(-93.0)
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,049 | $5,280 |
$2,196
14,654
kWh
|
$(-147.0)
-
MMBtu
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $636 | $3,800 |
$689
4,689
kWh
|
$(-53.0)
-
MMBtu
|
|
| TOTAL RECOMMENDED | $22,790 | $9,080 |
$24,358
120,163
kWh
|
$(-1,568.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,549 | $9,080 |
$20,781
104,337
kWh
|
$(-1,232.0)
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs